USULAN METODE PENJADWALAN JOB SHOP DI PT X MENGGUNAKAN ALGORITMA MATRIX HEURISTIC DENGAN MENGAKOMODASI PENJADWALAN ULANG

PT X is a company that produces specialized machines for the automotive industry using a Make-To-Order (MTO) production system. Based on primary data obtained from the company's ERP, it was found that 37.68% of operations experienced delays. Using a fishbone diagram, the researcher determine...

Full description

Saved in:
Bibliographic Details
Main Author: Christian Julian Tanaka, Angel
Format: Final Project
Language:Indonesia
Online Access:https://digilib.itb.ac.id/gdl/view/84138
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Institut Teknologi Bandung
Language: Indonesia
id id-itb.:84138
spelling id-itb.:841382024-08-14T09:38:40ZUSULAN METODE PENJADWALAN JOB SHOP DI PT X MENGGUNAKAN ALGORITMA MATRIX HEURISTIC DENGAN MENGAKOMODASI PENJADWALAN ULANG Christian Julian Tanaka, Angel Indonesia Final Project job shop scheduling, assembly, rescheduling, matrix heuristic algorithm, relative remaining processing time. INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/84138 PT X is a company that produces specialized machines for the automotive industry using a Make-To-Order (MTO) production system. Based on primary data obtained from the company's ERP, it was found that 37.68% of operations experienced delays. Using a fishbone diagram, the researcher determined that the focus of the problem to be solved from this research was the absence of a scheduling system that covers the assembly process and meets rescheduling needs. The job shop scheduling case in PT X is an NP-hard problem that needs to be solved using a heuristic algorithm. In this research, researchers will use a heuristic algorithm to develop a proposed scheduling method that includes the assembly stage and rescheduling requirements. After considering several alternative heuristic algorithms for the job shop case, this research proposes using the matrix heuristic algorithm as the method used for scheduling at PT X. This algorithm can be used for job shop scheduling and can process large amounts of data. Although this algorithm does not yet cover the assembly stage and meets rescheduling needs, it is flexible and can be developed to meet both the assembly and rescheduling stage needs. Researchers also propose using relative remaining processing time (RRP) as a priority dispatching rule and the earliest due date (EDD) as a tie-breaking rule for the matrix heuristic algorithm. Based on the results, the developed algorithm can produce a better solution for scheduling the production process of 5 products with a makespan reduction of 1292,2 hours or 12,37%. The reduction in makespan occurs because the RRP rule is used as a priority dispatching rule considering pacing and structural dependence factors. Apart from that, this algorithm can also accommodate rescheduling needs. text
institution Institut Teknologi Bandung
building Institut Teknologi Bandung Library
continent Asia
country Indonesia
Indonesia
content_provider Institut Teknologi Bandung
collection Digital ITB
language Indonesia
description PT X is a company that produces specialized machines for the automotive industry using a Make-To-Order (MTO) production system. Based on primary data obtained from the company's ERP, it was found that 37.68% of operations experienced delays. Using a fishbone diagram, the researcher determined that the focus of the problem to be solved from this research was the absence of a scheduling system that covers the assembly process and meets rescheduling needs. The job shop scheduling case in PT X is an NP-hard problem that needs to be solved using a heuristic algorithm. In this research, researchers will use a heuristic algorithm to develop a proposed scheduling method that includes the assembly stage and rescheduling requirements. After considering several alternative heuristic algorithms for the job shop case, this research proposes using the matrix heuristic algorithm as the method used for scheduling at PT X. This algorithm can be used for job shop scheduling and can process large amounts of data. Although this algorithm does not yet cover the assembly stage and meets rescheduling needs, it is flexible and can be developed to meet both the assembly and rescheduling stage needs. Researchers also propose using relative remaining processing time (RRP) as a priority dispatching rule and the earliest due date (EDD) as a tie-breaking rule for the matrix heuristic algorithm. Based on the results, the developed algorithm can produce a better solution for scheduling the production process of 5 products with a makespan reduction of 1292,2 hours or 12,37%. The reduction in makespan occurs because the RRP rule is used as a priority dispatching rule considering pacing and structural dependence factors. Apart from that, this algorithm can also accommodate rescheduling needs.
format Final Project
author Christian Julian Tanaka, Angel
spellingShingle Christian Julian Tanaka, Angel
USULAN METODE PENJADWALAN JOB SHOP DI PT X MENGGUNAKAN ALGORITMA MATRIX HEURISTIC DENGAN MENGAKOMODASI PENJADWALAN ULANG
author_facet Christian Julian Tanaka, Angel
author_sort Christian Julian Tanaka, Angel
title USULAN METODE PENJADWALAN JOB SHOP DI PT X MENGGUNAKAN ALGORITMA MATRIX HEURISTIC DENGAN MENGAKOMODASI PENJADWALAN ULANG
title_short USULAN METODE PENJADWALAN JOB SHOP DI PT X MENGGUNAKAN ALGORITMA MATRIX HEURISTIC DENGAN MENGAKOMODASI PENJADWALAN ULANG
title_full USULAN METODE PENJADWALAN JOB SHOP DI PT X MENGGUNAKAN ALGORITMA MATRIX HEURISTIC DENGAN MENGAKOMODASI PENJADWALAN ULANG
title_fullStr USULAN METODE PENJADWALAN JOB SHOP DI PT X MENGGUNAKAN ALGORITMA MATRIX HEURISTIC DENGAN MENGAKOMODASI PENJADWALAN ULANG
title_full_unstemmed USULAN METODE PENJADWALAN JOB SHOP DI PT X MENGGUNAKAN ALGORITMA MATRIX HEURISTIC DENGAN MENGAKOMODASI PENJADWALAN ULANG
title_sort usulan metode penjadwalan job shop di pt x menggunakan algoritma matrix heuristic dengan mengakomodasi penjadwalan ulang
url https://digilib.itb.ac.id/gdl/view/84138
_version_ 1822998434001453056