HYDRAULIC ANALYSIS AND FLOW ASSURANCE OF GAS TRUNKLINE & WATER INJECTION PIPELINE AT DAYUNG STATION FACILITIES, SOUTH SUMATRA

The high usage of crude oil and natural gas presents a challenge for oil & gas companies to maintain optimal production facilities. Performance degradation, such as decreased production well pressure, can reduce productivity. To address this, field life extension is necessary to optimize well pe...

Full description

Saved in:
Bibliographic Details
Main Author: Shadiqah, Sulthan
Format: Final Project
Language:Indonesia
Subjects:
Online Access:https://digilib.itb.ac.id/gdl/view/85410
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Institut Teknologi Bandung
Language: Indonesia
id id-itb.:85410
spelling id-itb.:854102024-08-20T13:30:59ZHYDRAULIC ANALYSIS AND FLOW ASSURANCE OF GAS TRUNKLINE & WATER INJECTION PIPELINE AT DAYUNG STATION FACILITIES, SOUTH SUMATRA Shadiqah, Sulthan Teknik (Rekayasa, enjinering dan kegiatan berkaitan) Indonesia Final Project Steady State Flow, Transient Flow, Hydraulic Analysis, Flow Assurance INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/85410 The high usage of crude oil and natural gas presents a challenge for oil & gas companies to maintain optimal production facilities. Performance degradation, such as decreased production well pressure, can reduce productivity. To address this, field life extension is necessary to optimize well performance and supporting facilities. Hydraulic analysis and the implementation of flow assurance concepts are required to ensure the success and safety of the process. This thesis aims to develop an accurate simulation model to provide operational recommendations through steady state analysis and to determine the pipeline safety factor related to transient phenomena such as water hammer and surge pressure during the field life extension phase of the gas trunkline and water injection pipeline facilities at Dayung Facilities. The reduction of suction pressure at Dayung Station is carried out to keep the production fluid flowrate stable. This phase involves variations in steady state case studies related to the flowrate of production fluid at specific times. The lowest recorded backpressure at Dayung is 913.522 psig and 1069.77 psig, and at Sumpal is 946.364 psig and 1098.03 psig, with a backpressure sensitivity of 0.221 psi/MMSCFD at Dayung. This sensitivity value can be used as input for selecting the low suction compressor to be installed. The smallest safety factor is 1.32 with a maximum surge pressure of 1021.60 psig, resulting from transient valve closure analysis at the Central Grissik Plant (CGP). Due to the aging production wells, the amount of produced water increases, so water injection can only be performed into the main injection well NS1 up to standard flowrates of 6824 BWPD at Dayung and 3500 BWPD at Sumpal, due to limitations in pump capacity. The alternative injection well Dayung WDW5 is projected to achieve a standard flowrate of 10,000 BWPD. Shifting the injection well causes water hammer phenomena due to valve closure at the mouth of well NS1. Transient analysis shows the smallest safety factor is 1.18, with the highest surge pressure of 1262.07 psig. text
institution Institut Teknologi Bandung
building Institut Teknologi Bandung Library
continent Asia
country Indonesia
Indonesia
content_provider Institut Teknologi Bandung
collection Digital ITB
language Indonesia
topic Teknik (Rekayasa, enjinering dan kegiatan berkaitan)
spellingShingle Teknik (Rekayasa, enjinering dan kegiatan berkaitan)
Shadiqah, Sulthan
HYDRAULIC ANALYSIS AND FLOW ASSURANCE OF GAS TRUNKLINE & WATER INJECTION PIPELINE AT DAYUNG STATION FACILITIES, SOUTH SUMATRA
description The high usage of crude oil and natural gas presents a challenge for oil & gas companies to maintain optimal production facilities. Performance degradation, such as decreased production well pressure, can reduce productivity. To address this, field life extension is necessary to optimize well performance and supporting facilities. Hydraulic analysis and the implementation of flow assurance concepts are required to ensure the success and safety of the process. This thesis aims to develop an accurate simulation model to provide operational recommendations through steady state analysis and to determine the pipeline safety factor related to transient phenomena such as water hammer and surge pressure during the field life extension phase of the gas trunkline and water injection pipeline facilities at Dayung Facilities. The reduction of suction pressure at Dayung Station is carried out to keep the production fluid flowrate stable. This phase involves variations in steady state case studies related to the flowrate of production fluid at specific times. The lowest recorded backpressure at Dayung is 913.522 psig and 1069.77 psig, and at Sumpal is 946.364 psig and 1098.03 psig, with a backpressure sensitivity of 0.221 psi/MMSCFD at Dayung. This sensitivity value can be used as input for selecting the low suction compressor to be installed. The smallest safety factor is 1.32 with a maximum surge pressure of 1021.60 psig, resulting from transient valve closure analysis at the Central Grissik Plant (CGP). Due to the aging production wells, the amount of produced water increases, so water injection can only be performed into the main injection well NS1 up to standard flowrates of 6824 BWPD at Dayung and 3500 BWPD at Sumpal, due to limitations in pump capacity. The alternative injection well Dayung WDW5 is projected to achieve a standard flowrate of 10,000 BWPD. Shifting the injection well causes water hammer phenomena due to valve closure at the mouth of well NS1. Transient analysis shows the smallest safety factor is 1.18, with the highest surge pressure of 1262.07 psig.
format Final Project
author Shadiqah, Sulthan
author_facet Shadiqah, Sulthan
author_sort Shadiqah, Sulthan
title HYDRAULIC ANALYSIS AND FLOW ASSURANCE OF GAS TRUNKLINE & WATER INJECTION PIPELINE AT DAYUNG STATION FACILITIES, SOUTH SUMATRA
title_short HYDRAULIC ANALYSIS AND FLOW ASSURANCE OF GAS TRUNKLINE & WATER INJECTION PIPELINE AT DAYUNG STATION FACILITIES, SOUTH SUMATRA
title_full HYDRAULIC ANALYSIS AND FLOW ASSURANCE OF GAS TRUNKLINE & WATER INJECTION PIPELINE AT DAYUNG STATION FACILITIES, SOUTH SUMATRA
title_fullStr HYDRAULIC ANALYSIS AND FLOW ASSURANCE OF GAS TRUNKLINE & WATER INJECTION PIPELINE AT DAYUNG STATION FACILITIES, SOUTH SUMATRA
title_full_unstemmed HYDRAULIC ANALYSIS AND FLOW ASSURANCE OF GAS TRUNKLINE & WATER INJECTION PIPELINE AT DAYUNG STATION FACILITIES, SOUTH SUMATRA
title_sort hydraulic analysis and flow assurance of gas trunkline & water injection pipeline at dayung station facilities, south sumatra
url https://digilib.itb.ac.id/gdl/view/85410
_version_ 1822010718122147840