PERHITUNGAN KEBUTUHAN DAYA LISTRIK PADA PROSES PEMBUATAN MINYAK DARI KELAPA SAWIT DI PT.PERKEBUNAN NUSANTARA VI (PERSERO) UNIT USAHA RIMBO DUA JAMBI
In the times like the current petroleum resource is non-renewable so we must maintain and use sparingly, especially on large industry for savings, or better use the power of his own example by using steam as the raw material in palm oil mill boiler is used as a generator. Thus the power consumption...
Saved in:
Main Authors: | , |
---|---|
Format: | Theses and Dissertations NonPeerReviewed |
Published: |
[Yogyakarta] : Universitas Gadjah Mada
2014
|
Subjects: | |
Online Access: | https://repository.ugm.ac.id/124847/ http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=65007 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Universitas Gadjah Mada |
id |
id-ugm-repo.124847 |
---|---|
record_format |
dspace |
spelling |
id-ugm-repo.1248472016-03-04T08:15:14Z https://repository.ugm.ac.id/124847/ PERHITUNGAN KEBUTUHAN DAYA LISTRIK PADA PROSES PEMBUATAN MINYAK DARI KELAPA SAWIT DI PT.PERKEBUNAN NUSANTARA VI (PERSERO) UNIT USAHA RIMBO DUA JAMBI , TIKA PRATIWI , Ir.Sri Lestari,MT. ETD In the times like the current petroleum resource is non-renewable so we must maintain and use sparingly, especially on large industry for savings, or better use the power of his own example by using steam as the raw material in palm oil mill boiler is used as a generator. Thus the power consumption required is not much use as fuel oil, boiler used 30Ton/TBS FFB capacity to produce 21.8 tons of vapor steam / hour so that it can turn a turbine with a capacity of 34 Kg / Kw so it can produce power of 600KwH , while the power required for 750KwH in the processing plant, the power shortage in the suply of generator in parallel with the turbine. The plant uses two turbines and two generators, turbine 1 is used as a processing engine in parallel with the turbine generator 1 while 2 as a backup if dala processing there is damage to the turbine generator 1 while the second is used for domestic power generation for residential now stop processing plant, the generator 2 is used for domestic power required for 125Kwh during operation stop the use of steam power generator's operating costs in the manufacturing of palm oil processing. [Yogyakarta] : Universitas Gadjah Mada 2014 Thesis NonPeerReviewed , TIKA PRATIWI and , Ir.Sri Lestari,MT. (2014) PERHITUNGAN KEBUTUHAN DAYA LISTRIK PADA PROSES PEMBUATAN MINYAK DARI KELAPA SAWIT DI PT.PERKEBUNAN NUSANTARA VI (PERSERO) UNIT USAHA RIMBO DUA JAMBI. UNSPECIFIED thesis, UNSPECIFIED. http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=65007 |
institution |
Universitas Gadjah Mada |
building |
UGM Library |
country |
Indonesia |
collection |
Repository Civitas UGM |
topic |
ETD |
spellingShingle |
ETD , TIKA PRATIWI , Ir.Sri Lestari,MT. PERHITUNGAN KEBUTUHAN DAYA LISTRIK PADA PROSES PEMBUATAN MINYAK DARI KELAPA SAWIT DI PT.PERKEBUNAN NUSANTARA VI (PERSERO) UNIT USAHA RIMBO DUA JAMBI |
description |
In the times like the current petroleum resource is non-renewable so we must
maintain and use sparingly, especially on large industry for savings, or better use the power
of his own example by using steam as the raw material in palm oil mill boiler is used as a
generator.
Thus the power consumption required is not much use as fuel oil, boiler used
30Ton/TBS FFB capacity to produce 21.8 tons of vapor steam / hour so that it can turn a
turbine with a capacity of 34 Kg / Kw so it can produce power of 600KwH , while the
power required for 750KwH in the processing plant, the power shortage in the suply of
generator in parallel with the turbine.
The plant uses two turbines and two generators, turbine 1 is used as a processing
engine in parallel with the turbine generator 1 while 2 as a backup if dala processing there
is damage to the turbine generator 1 while the second is used for domestic power
generation for residential now stop processing plant, the generator 2 is used for domestic
power required for 125Kwh during operation stop the use of steam power generator's
operating costs in the manufacturing of palm oil processing. |
format |
Theses and Dissertations NonPeerReviewed |
author |
, TIKA PRATIWI , Ir.Sri Lestari,MT. |
author_facet |
, TIKA PRATIWI , Ir.Sri Lestari,MT. |
author_sort |
, TIKA PRATIWI |
title |
PERHITUNGAN KEBUTUHAN DAYA LISTRIK PADA PROSES PEMBUATAN MINYAK DARI KELAPA SAWIT
DI PT.PERKEBUNAN NUSANTARA VI (PERSERO) UNIT USAHA RIMBO DUA JAMBI |
title_short |
PERHITUNGAN KEBUTUHAN DAYA LISTRIK PADA PROSES PEMBUATAN MINYAK DARI KELAPA SAWIT
DI PT.PERKEBUNAN NUSANTARA VI (PERSERO) UNIT USAHA RIMBO DUA JAMBI |
title_full |
PERHITUNGAN KEBUTUHAN DAYA LISTRIK PADA PROSES PEMBUATAN MINYAK DARI KELAPA SAWIT
DI PT.PERKEBUNAN NUSANTARA VI (PERSERO) UNIT USAHA RIMBO DUA JAMBI |
title_fullStr |
PERHITUNGAN KEBUTUHAN DAYA LISTRIK PADA PROSES PEMBUATAN MINYAK DARI KELAPA SAWIT
DI PT.PERKEBUNAN NUSANTARA VI (PERSERO) UNIT USAHA RIMBO DUA JAMBI |
title_full_unstemmed |
PERHITUNGAN KEBUTUHAN DAYA LISTRIK PADA PROSES PEMBUATAN MINYAK DARI KELAPA SAWIT
DI PT.PERKEBUNAN NUSANTARA VI (PERSERO) UNIT USAHA RIMBO DUA JAMBI |
title_sort |
perhitungan kebutuhan daya listrik pada proses pembuatan minyak dari kelapa sawit
di pt.perkebunan nusantara vi (persero) unit usaha rimbo dua jambi |
publisher |
[Yogyakarta] : Universitas Gadjah Mada |
publishDate |
2014 |
url |
https://repository.ugm.ac.id/124847/ http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=65007 |
_version_ |
1681232154980253696 |