KAJIAN DOKUMEN INSTRUKSI KERJA DAN PENERAPANNYA DI LAPANGAN (STUDI KASUS PADA PROYEK PEMBANGUNAN JEMBATAN IRONAYAN)
completed within A project generally has the goal to be the right cost, right quality, on time and done safely. One attempt to reach the project goal is by doing each job with work instructions so that work can be done efficiently and effectively. The Regulation of the Minister of Public Works No. 0...
Saved in:
Main Authors: | , |
---|---|
Format: | Theses and Dissertations NonPeerReviewed |
Published: |
[Yogyakarta] : Universitas Gadjah Mada
2014
|
Subjects: | |
Online Access: | https://repository.ugm.ac.id/127551/ http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=67812 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Universitas Gadjah Mada |
Summary: | completed within A project generally has the goal to be the right cost, right
quality, on time and done safely. One attempt to reach the project goal is by doing
each job with work instructions so that work can be done efficiently and
effectively. The Regulation of the Minister of Public Works No. 04/PRT/M/2009
has required that the contractor has to make contract quality plan or called RMK
(Rencana Mutu Kontrak). RMK is quality plan implementation and aims to be the
quality assurance activities for the process and results of operations as required
the work and the inside of RMK has work instructions.
The purpose of this study is to evaluate the work instruction and give improvement
for the work instruction document based on a case study of Ironayan bridge
project located in Bantul, Daerah Istimewa Yogyakarta, by doing case study in
there. This study is done by observation and then make work instructions based on
theory in preparing work instructions, that is detailing the job with WBS, sorting
the steps of worksusing network diagram and then write the narration of work
instructions. Then this study comparing the work instruction in RMK and from the
evaluation of this study.
The result of this study found that the work instructions from RMK is not detailed
enough. Some implementation in the field is not match with work instruction in
RMK. The bridge structure�s work method (consist of fondation, abutment and
girder work)have been documented in this study. This study also give a work
instruction for several works in this bridge project. Based on the observation and
WBS analysis that have been done, the work instructions for segmental precast
prestress bridge�s work can be presented in more detail. |
---|