Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia
The paper main purposes are to understanding the actual inefficiency level in heavy ccheck B-737 NG project execution process at PT GMF Aeroasia, identify the critical activities, and the priority of the lateness risk source in a project planning step. This research is focus on the scheduling proces...
Saved in:
Main Authors: | , |
---|---|
Format: | Theses and Dissertations NonPeerReviewed |
Published: |
[Yogyakarta] : Universitas Gadjah Mada
2012
|
Subjects: | |
Online Access: | https://repository.ugm.ac.id/98872/ http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=54912 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Universitas Gadjah Mada |
id |
id-ugm-repo.98872 |
---|---|
record_format |
dspace |
spelling |
id-ugm-repo.988722016-03-04T08:45:40Z https://repository.ugm.ac.id/98872/ Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia , Anugroho Narotomo Gartam , Dr. Kuncoro Hartowidodo, M.Eng. ETD The paper main purposes are to understanding the actual inefficiency level in heavy ccheck B-737 NG project execution process at PT GMF Aeroasia, identify the critical activities, and the priority of the lateness risk source in a project planning step. This research is focus on the scheduling process and the project risk management, by using Program Evaluation and Review Technique (PERT) and Project Risk Failure Mode and Effect Analysis (RFMEA) methods. Based to the historical information of heavy c-check B-737 NG Turn Around Time (TAT) value at PT GMF Aeroasia between 2008 and 2011, ascertainable if there�s a significant deviation between the average of contract TAT value and the average of actual TAT value. The main purpose of PERT in this project is to find out the optimal TAT value of the project and identify the critical activities in this project. The optimal TAT value can be defined as the total duration of the project critical path, while the critical activities that identified in this project is used as the variable in the RFMEA analysis process. The result of RFMEA analysis gave information about the priority of the project lateness risk source. Project Risk Priority Number (RPN) is the outcome of the calculation between the risk score and the risk detection ability. The combination of the RPN and risk score on the scatter plot shows the project lateness risk source. According to information that shown at the Pareto diagram of RPN, risk score and the scatter plot, the source of lateness problem in the heavy ccheck B-737 NG at PT GMF Aeroasia is the material availability in engine and pylon, fuselage and cargo, hydraulic and landing gear, and cabin area. [Yogyakarta] : Universitas Gadjah Mada 2012 Thesis NonPeerReviewed , Anugroho Narotomo Gartam and , Dr. Kuncoro Hartowidodo, M.Eng. (2012) Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia. UNSPECIFIED thesis, UNSPECIFIED. http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=54912 |
institution |
Universitas Gadjah Mada |
building |
UGM Library |
country |
Indonesia |
collection |
Repository Civitas UGM |
topic |
ETD |
spellingShingle |
ETD , Anugroho Narotomo Gartam , Dr. Kuncoro Hartowidodo, M.Eng. Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia |
description |
The paper main purposes are to understanding the actual inefficiency level in heavy ccheck
B-737 NG project execution process at PT GMF Aeroasia, identify the critical activities,
and the priority of the lateness risk source in a project planning step. This research is focus on
the scheduling process and the project risk management, by using Program Evaluation and
Review Technique (PERT) and Project Risk Failure Mode and Effect Analysis (RFMEA)
methods.
Based to the historical information of heavy c-check B-737 NG Turn Around Time
(TAT) value at PT GMF Aeroasia between 2008 and 2011, ascertainable if there�s a significant
deviation between the average of contract TAT value and the average of actual TAT value. The
main purpose of PERT in this project is to find out the optimal TAT value of the project and
identify the critical activities in this project. The optimal TAT value can be defined as the total
duration of the project critical path, while the critical activities that identified in this project is
used as the variable in the RFMEA analysis process.
The result of RFMEA analysis gave information about the priority of the project lateness
risk source. Project Risk Priority Number (RPN) is the outcome of the calculation between the
risk score and the risk detection ability. The combination of the RPN and risk score on the scatter
plot shows the project lateness risk source. According to information that shown at the Pareto
diagram of RPN, risk score and the scatter plot, the source of lateness problem in the heavy ccheck
B-737 NG at PT GMF Aeroasia is the material availability in engine and pylon, fuselage
and cargo, hydraulic and landing gear, and cabin area. |
format |
Theses and Dissertations NonPeerReviewed |
author |
, Anugroho Narotomo Gartam , Dr. Kuncoro Hartowidodo, M.Eng. |
author_facet |
, Anugroho Narotomo Gartam , Dr. Kuncoro Hartowidodo, M.Eng. |
author_sort |
, Anugroho Narotomo Gartam |
title |
Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia |
title_short |
Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia |
title_full |
Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia |
title_fullStr |
Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia |
title_full_unstemmed |
Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia |
title_sort |
implementasi program evaluation and review technique (pert) dan project risk failure mode and effect analysis (rfmea) untuk optimalisasi nilai turn around time (tat) proyek heavy c-check b-737 ng di pt gmf aeroasia |
publisher |
[Yogyakarta] : Universitas Gadjah Mada |
publishDate |
2012 |
url |
https://repository.ugm.ac.id/98872/ http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=54912 |
_version_ |
1681230438913277952 |