Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia

The paper main purposes are to understanding the actual inefficiency level in heavy ccheck B-737 NG project execution process at PT GMF Aeroasia, identify the critical activities, and the priority of the lateness risk source in a project planning step. This research is focus on the scheduling proces...

Full description

Saved in:
Bibliographic Details
Main Authors: , Anugroho Narotomo Gartam, , Dr. Kuncoro Hartowidodo, M.Eng.
Format: Theses and Dissertations NonPeerReviewed
Published: [Yogyakarta] : Universitas Gadjah Mada 2012
Subjects:
ETD
Online Access:https://repository.ugm.ac.id/98872/
http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=54912
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Universitas Gadjah Mada
id id-ugm-repo.98872
record_format dspace
spelling id-ugm-repo.988722016-03-04T08:45:40Z https://repository.ugm.ac.id/98872/ Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia , Anugroho Narotomo Gartam , Dr. Kuncoro Hartowidodo, M.Eng. ETD The paper main purposes are to understanding the actual inefficiency level in heavy ccheck B-737 NG project execution process at PT GMF Aeroasia, identify the critical activities, and the priority of the lateness risk source in a project planning step. This research is focus on the scheduling process and the project risk management, by using Program Evaluation and Review Technique (PERT) and Project Risk Failure Mode and Effect Analysis (RFMEA) methods. Based to the historical information of heavy c-check B-737 NG Turn Around Time (TAT) value at PT GMF Aeroasia between 2008 and 2011, ascertainable if there�s a significant deviation between the average of contract TAT value and the average of actual TAT value. The main purpose of PERT in this project is to find out the optimal TAT value of the project and identify the critical activities in this project. The optimal TAT value can be defined as the total duration of the project critical path, while the critical activities that identified in this project is used as the variable in the RFMEA analysis process. The result of RFMEA analysis gave information about the priority of the project lateness risk source. Project Risk Priority Number (RPN) is the outcome of the calculation between the risk score and the risk detection ability. The combination of the RPN and risk score on the scatter plot shows the project lateness risk source. According to information that shown at the Pareto diagram of RPN, risk score and the scatter plot, the source of lateness problem in the heavy ccheck B-737 NG at PT GMF Aeroasia is the material availability in engine and pylon, fuselage and cargo, hydraulic and landing gear, and cabin area. [Yogyakarta] : Universitas Gadjah Mada 2012 Thesis NonPeerReviewed , Anugroho Narotomo Gartam and , Dr. Kuncoro Hartowidodo, M.Eng. (2012) Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia. UNSPECIFIED thesis, UNSPECIFIED. http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=54912
institution Universitas Gadjah Mada
building UGM Library
country Indonesia
collection Repository Civitas UGM
topic ETD
spellingShingle ETD
, Anugroho Narotomo Gartam
, Dr. Kuncoro Hartowidodo, M.Eng.
Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia
description The paper main purposes are to understanding the actual inefficiency level in heavy ccheck B-737 NG project execution process at PT GMF Aeroasia, identify the critical activities, and the priority of the lateness risk source in a project planning step. This research is focus on the scheduling process and the project risk management, by using Program Evaluation and Review Technique (PERT) and Project Risk Failure Mode and Effect Analysis (RFMEA) methods. Based to the historical information of heavy c-check B-737 NG Turn Around Time (TAT) value at PT GMF Aeroasia between 2008 and 2011, ascertainable if there�s a significant deviation between the average of contract TAT value and the average of actual TAT value. The main purpose of PERT in this project is to find out the optimal TAT value of the project and identify the critical activities in this project. The optimal TAT value can be defined as the total duration of the project critical path, while the critical activities that identified in this project is used as the variable in the RFMEA analysis process. The result of RFMEA analysis gave information about the priority of the project lateness risk source. Project Risk Priority Number (RPN) is the outcome of the calculation between the risk score and the risk detection ability. The combination of the RPN and risk score on the scatter plot shows the project lateness risk source. According to information that shown at the Pareto diagram of RPN, risk score and the scatter plot, the source of lateness problem in the heavy ccheck B-737 NG at PT GMF Aeroasia is the material availability in engine and pylon, fuselage and cargo, hydraulic and landing gear, and cabin area.
format Theses and Dissertations
NonPeerReviewed
author , Anugroho Narotomo Gartam
, Dr. Kuncoro Hartowidodo, M.Eng.
author_facet , Anugroho Narotomo Gartam
, Dr. Kuncoro Hartowidodo, M.Eng.
author_sort , Anugroho Narotomo Gartam
title Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia
title_short Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia
title_full Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia
title_fullStr Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia
title_full_unstemmed Implementasi Program Evaluation and Review Technique (PERT) dan Project Risk Failure Mode and Effect Analysis (RFMEA) Untuk Optimalisasi Nilai Turn Around Time (TAT) Proyek Heavy C-check B-737 NG di PT GMF Aeroasia
title_sort implementasi program evaluation and review technique (pert) dan project risk failure mode and effect analysis (rfmea) untuk optimalisasi nilai turn around time (tat) proyek heavy c-check b-737 ng di pt gmf aeroasia
publisher [Yogyakarta] : Universitas Gadjah Mada
publishDate 2012
url https://repository.ugm.ac.id/98872/
http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=54912
_version_ 1681230438913277952