Build Operate and Transfer (BOT) in power plant projects in Iran
Iranian electric power industry has adopted Build Operate Transfer (BOT) approach in a number of projects as an alternative to utilize private sector investment. Therefore, some power plant projects have been successfully implemented through BOT such as South Isfahan power plant as a first BOT power...
Saved in:
Main Authors: | , |
---|---|
Format: | Conference or Workshop Item |
Published: |
2012
|
Subjects: | |
Online Access: | http://eprints.utm.my/id/eprint/34356/ |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Universiti Teknologi Malaysia |
id |
my.utm.34356 |
---|---|
record_format |
eprints |
spelling |
my.utm.343562017-09-06T08:19:38Z http://eprints.utm.my/id/eprint/34356/ Build Operate and Transfer (BOT) in power plant projects in Iran Md. Yusof, Aminah Salami, Bahman TA Engineering (General). Civil engineering (General) Iranian electric power industry has adopted Build Operate Transfer (BOT) approach in a number of projects as an alternative to utilize private sector investment. Therefore, some power plant projects have been successfully implemented through BOT such as South Isfahan power plant as a first BOT power plant; in contrast, some of them have been failed in the procurement process. Thus, there is a need for improving procurement approaches for future BOT projects. This study identifies and analysis various success factors in BOT power plant projects in Iran. The research methodology that has been utilized including literature review, and survey questionnaire have distributed to BOT experts. Hence, this research establishes success factors for BOT power plant project in Iran comprise of 33 factors. All 33 success factors are considered as important factors in BOT infrastructure projects; moreover, there is a good agreement in significance of success factors between government organization, consultants, and concessionaires. 2012 Conference or Workshop Item PeerReviewed Md. Yusof, Aminah and Salami, Bahman (2012) Build Operate and Transfer (BOT) in power plant projects in Iran. In: Conference. |
institution |
Universiti Teknologi Malaysia |
building |
UTM Library |
collection |
Institutional Repository |
continent |
Asia |
country |
Malaysia |
content_provider |
Universiti Teknologi Malaysia |
content_source |
UTM Institutional Repository |
url_provider |
http://eprints.utm.my/ |
topic |
TA Engineering (General). Civil engineering (General) |
spellingShingle |
TA Engineering (General). Civil engineering (General) Md. Yusof, Aminah Salami, Bahman Build Operate and Transfer (BOT) in power plant projects in Iran |
description |
Iranian electric power industry has adopted Build Operate Transfer (BOT) approach in a number of projects as an alternative to utilize private sector investment. Therefore, some power plant projects have been successfully implemented through BOT such as South Isfahan power plant as a first BOT power plant; in contrast, some of them have been failed in the procurement process. Thus, there is a need for improving procurement approaches for future BOT projects. This study identifies and analysis various success factors in BOT power plant projects in Iran. The research methodology that has been utilized including literature review, and survey questionnaire have distributed to BOT experts. Hence, this research establishes success factors for BOT power plant project in Iran comprise of 33 factors. All 33 success factors are considered as important factors in BOT infrastructure projects; moreover, there is a good agreement in significance of success factors between government organization, consultants, and concessionaires. |
format |
Conference or Workshop Item |
author |
Md. Yusof, Aminah Salami, Bahman |
author_facet |
Md. Yusof, Aminah Salami, Bahman |
author_sort |
Md. Yusof, Aminah |
title |
Build Operate and Transfer (BOT) in power plant projects in Iran |
title_short |
Build Operate and Transfer (BOT) in power plant projects in Iran |
title_full |
Build Operate and Transfer (BOT) in power plant projects in Iran |
title_fullStr |
Build Operate and Transfer (BOT) in power plant projects in Iran |
title_full_unstemmed |
Build Operate and Transfer (BOT) in power plant projects in Iran |
title_sort |
build operate and transfer (bot) in power plant projects in iran |
publishDate |
2012 |
url |
http://eprints.utm.my/id/eprint/34356/ |
_version_ |
1643649565312679936 |