A study in minimizing the 15.88% production loss in the production of coat at Onesimus Corporation amounting to Php 10,350,169.98 from the month of June-November 2013.
This practicum study is about minimizing the 15.88% productivity loss of coat in Onesimus Corporation for the Month of June to November 2013. The factors that caused delay in the production have been identified and planned an action for each of them. These factors that contribute to delays are th...
Saved in:
Main Author: | |
---|---|
Format: | Theses and Dissertations NonPeerReviewed |
Published: |
2014
|
Subjects: | |
Online Access: | http://thesis.dlsud.edu.ph/221/7/NuestroJJ%20...%20-%20OnesimusCorporation.pdf http://thesis.dlsud.edu.ph/221/ |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | De La Salle University |
Summary: | This practicum study is about minimizing the 15.88% productivity loss of coat in
Onesimus Corporation for the Month of June to November 2013. The factors that
caused delay in the production have been identified and planned an action for
each of them. These factors that contribute to delays are the standard procedure
was not followed by the operator, Corrective maintenance of the sewing machine
and inappropriate design chair. The objective of this study is to minimize the
delay caused by man, which is to give sanctions on who will not follow the
standard procedure, Implement a preventive maintenance program, lastly
purchasing appropriate chair to lessen the body pain of the workers. |
---|