A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations
This research examines the performance of 13 dispatching rules for executing a resource-constrained project whose estimated activity durations may differ from the actual activity durations. The dispatching rules are tested in environments characterized by three factors, namely, the order strength of...
Saved in:
Main Author: | |
---|---|
Format: | text |
Language: | English |
Published: |
Institutional Knowledge at Singapore Management University
1998
|
Subjects: | |
Online Access: | https://ink.library.smu.edu.sg/lkcsb_research/2220 https://doi.org/10.1016/s0305-0483(98)00021-8 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Singapore Management University |
Language: | English |
id |
sg-smu-ink.lkcsb_research-3219 |
---|---|
record_format |
dspace |
spelling |
sg-smu-ink.lkcsb_research-32192010-09-23T12:30:04Z A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations Yang, Kum Khiong This research examines the performance of 13 dispatching rules for executing a resource-constrained project whose estimated activity durations may differ from the actual activity durations. The dispatching rules are tested in environments characterized by three factors, namely, the order strength of the precedence relationship, the level of resource availability and the level of estimation errors in the activity durations. The results show that project environment affects only the performance differences but not the grouping of the better dispatching rules. The greatest number of successors, rank positional weight, greatest cumulative resource requirement and minimum activity slack dispatching rules consistently perform better than the other dispatching rules, unaffected by the accuracy of the estimated activity durations. This finding validates the results of many past studies in the deterministic project environment for choosing the right dispatching rule for both projects with and without well-estimated activity durations. 1998-01-01T08:00:00Z text https://ink.library.smu.edu.sg/lkcsb_research/2220 info:doi/10.1016/s0305-0483(98)00021-8 https://doi.org/10.1016/s0305-0483(98)00021-8 Research Collection Lee Kong Chian School Of Business eng Institutional Knowledge at Singapore Management University project management heuristics dispatching simulation Business |
institution |
Singapore Management University |
building |
SMU Libraries |
continent |
Asia |
country |
Singapore Singapore |
content_provider |
SMU Libraries |
collection |
InK@SMU |
language |
English |
topic |
project management heuristics dispatching simulation Business |
spellingShingle |
project management heuristics dispatching simulation Business Yang, Kum Khiong A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations |
description |
This research examines the performance of 13 dispatching rules for executing a resource-constrained project whose estimated activity durations may differ from the actual activity durations. The dispatching rules are tested in environments characterized by three factors, namely, the order strength of the precedence relationship, the level of resource availability and the level of estimation errors in the activity durations. The results show that project environment affects only the performance differences but not the grouping of the better dispatching rules. The greatest number of successors, rank positional weight, greatest cumulative resource requirement and minimum activity slack dispatching rules consistently perform better than the other dispatching rules, unaffected by the accuracy of the estimated activity durations. This finding validates the results of many past studies in the deterministic project environment for choosing the right dispatching rule for both projects with and without well-estimated activity durations. |
format |
text |
author |
Yang, Kum Khiong |
author_facet |
Yang, Kum Khiong |
author_sort |
Yang, Kum Khiong |
title |
A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations |
title_short |
A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations |
title_full |
A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations |
title_fullStr |
A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations |
title_full_unstemmed |
A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations |
title_sort |
comparison of dispatching rules for executing a resource-constrained project with estimated activity durations |
publisher |
Institutional Knowledge at Singapore Management University |
publishDate |
1998 |
url |
https://ink.library.smu.edu.sg/lkcsb_research/2220 https://doi.org/10.1016/s0305-0483(98)00021-8 |
_version_ |
1770570179429793792 |