A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations

This research examines the performance of 13 dispatching rules for executing a resource-constrained project whose estimated activity durations may differ from the actual activity durations. The dispatching rules are tested in environments characterized by three factors, namely, the order strength of...

Full description

Saved in:
Bibliographic Details
Main Author: Yang, Kum Khiong
Format: text
Language:English
Published: Institutional Knowledge at Singapore Management University 1998
Subjects:
Online Access:https://ink.library.smu.edu.sg/lkcsb_research/2220
https://doi.org/10.1016/s0305-0483(98)00021-8
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Singapore Management University
Language: English
id sg-smu-ink.lkcsb_research-3219
record_format dspace
spelling sg-smu-ink.lkcsb_research-32192010-09-23T12:30:04Z A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations Yang, Kum Khiong This research examines the performance of 13 dispatching rules for executing a resource-constrained project whose estimated activity durations may differ from the actual activity durations. The dispatching rules are tested in environments characterized by three factors, namely, the order strength of the precedence relationship, the level of resource availability and the level of estimation errors in the activity durations. The results show that project environment affects only the performance differences but not the grouping of the better dispatching rules. The greatest number of successors, rank positional weight, greatest cumulative resource requirement and minimum activity slack dispatching rules consistently perform better than the other dispatching rules, unaffected by the accuracy of the estimated activity durations. This finding validates the results of many past studies in the deterministic project environment for choosing the right dispatching rule for both projects with and without well-estimated activity durations. 1998-01-01T08:00:00Z text https://ink.library.smu.edu.sg/lkcsb_research/2220 info:doi/10.1016/s0305-0483(98)00021-8 https://doi.org/10.1016/s0305-0483(98)00021-8 Research Collection Lee Kong Chian School Of Business eng Institutional Knowledge at Singapore Management University project management heuristics dispatching simulation Business
institution Singapore Management University
building SMU Libraries
continent Asia
country Singapore
Singapore
content_provider SMU Libraries
collection InK@SMU
language English
topic project management
heuristics
dispatching
simulation
Business
spellingShingle project management
heuristics
dispatching
simulation
Business
Yang, Kum Khiong
A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations
description This research examines the performance of 13 dispatching rules for executing a resource-constrained project whose estimated activity durations may differ from the actual activity durations. The dispatching rules are tested in environments characterized by three factors, namely, the order strength of the precedence relationship, the level of resource availability and the level of estimation errors in the activity durations. The results show that project environment affects only the performance differences but not the grouping of the better dispatching rules. The greatest number of successors, rank positional weight, greatest cumulative resource requirement and minimum activity slack dispatching rules consistently perform better than the other dispatching rules, unaffected by the accuracy of the estimated activity durations. This finding validates the results of many past studies in the deterministic project environment for choosing the right dispatching rule for both projects with and without well-estimated activity durations.
format text
author Yang, Kum Khiong
author_facet Yang, Kum Khiong
author_sort Yang, Kum Khiong
title A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations
title_short A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations
title_full A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations
title_fullStr A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations
title_full_unstemmed A Comparison of Dispatching Rules for Executing a Resource-Constrained Project with Estimated Activity Durations
title_sort comparison of dispatching rules for executing a resource-constrained project with estimated activity durations
publisher Institutional Knowledge at Singapore Management University
publishDate 1998
url https://ink.library.smu.edu.sg/lkcsb_research/2220
https://doi.org/10.1016/s0305-0483(98)00021-8
_version_ 1770570179429793792