Effects of Erroneous Estimation of Activity Durations on Scheduling and Dispatching a Single Project
A study examines the effects of erroneous estimation of activity durations on 2 different approaches for executing a resource-constrained project. The 2 approaches are scheduling and dispatching. The results show that scheduling generally produces a shorter project completion time than the heuristic...
Saved in:
Main Author: | |
---|---|
Format: | text |
Language: | English |
Published: |
Institutional Knowledge at Singapore Management University
1996
|
Subjects: | |
Online Access: | https://ink.library.smu.edu.sg/lkcsb_research/2222 https://proquest.umi.com/pqdlink?did=10057992&sid=7&Fmt=4&clientId=44274&RQT=309&VName=PQD |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Singapore Management University |
Language: | English |
id |
sg-smu-ink.lkcsb_research-3221 |
---|---|
record_format |
dspace |
spelling |
sg-smu-ink.lkcsb_research-32212010-09-23T12:30:04Z Effects of Erroneous Estimation of Activity Durations on Scheduling and Dispatching a Single Project Yang, Kum Khiong A study examines the effects of erroneous estimation of activity durations on 2 different approaches for executing a resource-constrained project. The 2 approaches are scheduling and dispatching. The results show that scheduling generally produces a shorter project completion time than the heuristic dispatching rules. Results also indicate that project environment affects only the relative performance differences of the scheduling and dispatching rules but not their ranking. Frequent rescheduling improves the project completion time, while the timing of rescheduling has little impact on the improvement in the project completion time. 1996-01-01T08:00:00Z text https://ink.library.smu.edu.sg/lkcsb_research/2222 info:doi/10.1111/j.1540-5915.1996.tb00853.x https://proquest.umi.com/pqdlink?did=10057992&sid=7&Fmt=4&clientId=44274&RQT=309&VName=PQD Research Collection Lee Kong Chian School Of Business eng Institutional Knowledge at Singapore Management University Business |
institution |
Singapore Management University |
building |
SMU Libraries |
continent |
Asia |
country |
Singapore Singapore |
content_provider |
SMU Libraries |
collection |
InK@SMU |
language |
English |
topic |
Business |
spellingShingle |
Business Yang, Kum Khiong Effects of Erroneous Estimation of Activity Durations on Scheduling and Dispatching a Single Project |
description |
A study examines the effects of erroneous estimation of activity durations on 2 different approaches for executing a resource-constrained project. The 2 approaches are scheduling and dispatching. The results show that scheduling generally produces a shorter project completion time than the heuristic dispatching rules. Results also indicate that project environment affects only the relative performance differences of the scheduling and dispatching rules but not their ranking. Frequent rescheduling improves the project completion time, while the timing of rescheduling has little impact on the improvement in the project completion time. |
format |
text |
author |
Yang, Kum Khiong |
author_facet |
Yang, Kum Khiong |
author_sort |
Yang, Kum Khiong |
title |
Effects of Erroneous Estimation of Activity Durations on Scheduling and Dispatching a Single Project |
title_short |
Effects of Erroneous Estimation of Activity Durations on Scheduling and Dispatching a Single Project |
title_full |
Effects of Erroneous Estimation of Activity Durations on Scheduling and Dispatching a Single Project |
title_fullStr |
Effects of Erroneous Estimation of Activity Durations on Scheduling and Dispatching a Single Project |
title_full_unstemmed |
Effects of Erroneous Estimation of Activity Durations on Scheduling and Dispatching a Single Project |
title_sort |
effects of erroneous estimation of activity durations on scheduling and dispatching a single project |
publisher |
Institutional Knowledge at Singapore Management University |
publishDate |
1996 |
url |
https://ink.library.smu.edu.sg/lkcsb_research/2222 https://proquest.umi.com/pqdlink?did=10057992&sid=7&Fmt=4&clientId=44274&RQT=309&VName=PQD |
_version_ |
1770570180429086720 |