Effects of Erroneous Estimation of Activity Durations on Scheduling and Dispatching a Single Project
A study examines the effects of erroneous estimation of activity durations on 2 different approaches for executing a resource-constrained project. The 2 approaches are scheduling and dispatching. The results show that scheduling generally produces a shorter project completion time than the heuristic...