Grasberg block cave underground mining will be started in 2016. As a primary access for man and material, AB Tunnel has been building since 2004 using drill and blast tunneling method. With primary sequences are 1) Drilling face, 2) charging and blasting, 3) mucking and hauling, 4) ground supporting...

Full description

Saved in:
Bibliographic Details
Main Author: HABIBIE (NIM 12104017), RIZKI
Format: Final Project
Language:Indonesia
Online Access:https://digilib.itb.ac.id/gdl/view/12593
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Institut Teknologi Bandung
Language: Indonesia
id id-itb.:12593
spelling id-itb.:125932017-09-27T10:39:04Z#TITLE_ALTERNATIVE# HABIBIE (NIM 12104017), RIZKI Indonesia Final Project INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/12593 Grasberg block cave underground mining will be started in 2016. As a primary access for man and material, AB Tunnel has been building since 2004 using drill and blast tunneling method. With primary sequences are 1) Drilling face, 2) charging and blasting, 3) mucking and hauling, 4) ground supporting and 5) shotcrete. In the last few months, tunnel advance target was not achieved. One of the causes is no target scheduling. Therefore, an operational scheduling with actual condition consideration tried to be made as a solution in order to obtain monthly target.<p> <br /> <br /> <br /> <br /> <br /> Researches started with statistical calculation for 5 primary stages completion time from historical and field observation data. Based on the calculation, we got the minimum, average and maximum time needed for completing 1 tunneling cycle. As seen, ground supporting have a biggest average percentage and biggest time usage deviation. Thus, for reducing time usage for this stage, a detail theoretical approach has done by considering some aspects a) drilling velocity correlated to rock mass condition and drilling tool specification, b) split set spacing, c) standard pattern to set up split set and weld mesh, c) actual mechanical availability.<p> <br /> <br /> <br /> <br /> <br /> After average time usage for 5 stages has gotten, then refer to equipment usage limit and actual tunneling rule, an operational scheduling scheme for 3 heading in GBC Terminal was recommended. This scheme can be used as a work achievement schedule for obtaining monthly advance target. text
institution Institut Teknologi Bandung
building Institut Teknologi Bandung Library
continent Asia
country Indonesia
Indonesia
content_provider Institut Teknologi Bandung
collection Digital ITB
language Indonesia
description Grasberg block cave underground mining will be started in 2016. As a primary access for man and material, AB Tunnel has been building since 2004 using drill and blast tunneling method. With primary sequences are 1) Drilling face, 2) charging and blasting, 3) mucking and hauling, 4) ground supporting and 5) shotcrete. In the last few months, tunnel advance target was not achieved. One of the causes is no target scheduling. Therefore, an operational scheduling with actual condition consideration tried to be made as a solution in order to obtain monthly target.<p> <br /> <br /> <br /> <br /> <br /> Researches started with statistical calculation for 5 primary stages completion time from historical and field observation data. Based on the calculation, we got the minimum, average and maximum time needed for completing 1 tunneling cycle. As seen, ground supporting have a biggest average percentage and biggest time usage deviation. Thus, for reducing time usage for this stage, a detail theoretical approach has done by considering some aspects a) drilling velocity correlated to rock mass condition and drilling tool specification, b) split set spacing, c) standard pattern to set up split set and weld mesh, c) actual mechanical availability.<p> <br /> <br /> <br /> <br /> <br /> After average time usage for 5 stages has gotten, then refer to equipment usage limit and actual tunneling rule, an operational scheduling scheme for 3 heading in GBC Terminal was recommended. This scheme can be used as a work achievement schedule for obtaining monthly advance target.
format Final Project
author HABIBIE (NIM 12104017), RIZKI
spellingShingle HABIBIE (NIM 12104017), RIZKI
#TITLE_ALTERNATIVE#
author_facet HABIBIE (NIM 12104017), RIZKI
author_sort HABIBIE (NIM 12104017), RIZKI
title #TITLE_ALTERNATIVE#
title_short #TITLE_ALTERNATIVE#
title_full #TITLE_ALTERNATIVE#
title_fullStr #TITLE_ALTERNATIVE#
title_full_unstemmed #TITLE_ALTERNATIVE#
title_sort #title_alternative#
url https://digilib.itb.ac.id/gdl/view/12593
_version_ 1820728566528081920