PROPOSAL OF DEVELOPMENT ACCELERATION IN DMLZ UNDERGROUND MINE AT PT. FREEPORT INDONESIA
Toward the DMLZ Mine Production commissioning on January 2015, DMLZ Engineering Group needs to accelerate development activities in order to avoid project behind schedule. Actual achievement average on year of 2010 is 284 m-Deq per month while target per months along 2011 is 360 m-Deq per month. Tar...