STUDY DESIGN LAMONG BAY RECLAMATION CONSTRUCTION USING GROUND IMPROVEMENT VIBRO COMPACTION AND PREFABRICATED VERTICAL DRAIN WITH FINITE ELEMENT METHOD
Breakwater structure is built on a reclamation area in Lamong Bay because the ground water level is high enough so the sand embankment must be supported by breakwater to make the embankment still stands in the staged construction. Because the subsoil consists of soft soil, the structure of the break...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/23917 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:23917 |
---|---|
spelling |
id-itb.:239172017-12-08T13:05:05ZSTUDY DESIGN LAMONG BAY RECLAMATION CONSTRUCTION USING GROUND IMPROVEMENT VIBRO COMPACTION AND PREFABRICATED VERTICAL DRAIN WITH FINITE ELEMENT METHOD ANDRESON, REY Teknik sipil Indonesia Final Project INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/23917 Breakwater structure is built on a reclamation area in Lamong Bay because the ground water level is high enough so the sand embankment must be supported by breakwater to make the embankment still stands in the staged construction. Because the subsoil consists of soft soil, the structure of the breakwater should be given the reinforcement so that the soil does not collapse, such as the construction of a bamboo matrass and bamboo cluster under the structure of the breakwater. <br /> <br /> <br /> Ground improvement in this reclamation area using Prefabricated Vertical Drain. triangular configuration with spacing of 1 meter. Construction of the sand embankment is done in stages so the embankment will not collapse and increase bearing capacity (gained strength) through the consolidation process. Because of the material of the embankment is sand, so there is a potential for liquefaction, therefore the embankment need the improvement using Vibro Compaction. <br /> <br /> <br /> PLAXIS 2D will give the model for finite element method and slope stability analysis. The results of slope stability analysis by PLAXIS 2D shown the embankment conditions, earthquakes, and service life meets the requirements of SF minimum value. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
topic |
Teknik sipil |
spellingShingle |
Teknik sipil ANDRESON, REY STUDY DESIGN LAMONG BAY RECLAMATION CONSTRUCTION USING GROUND IMPROVEMENT VIBRO COMPACTION AND PREFABRICATED VERTICAL DRAIN WITH FINITE ELEMENT METHOD |
description |
Breakwater structure is built on a reclamation area in Lamong Bay because the ground water level is high enough so the sand embankment must be supported by breakwater to make the embankment still stands in the staged construction. Because the subsoil consists of soft soil, the structure of the breakwater should be given the reinforcement so that the soil does not collapse, such as the construction of a bamboo matrass and bamboo cluster under the structure of the breakwater. <br />
<br />
<br />
Ground improvement in this reclamation area using Prefabricated Vertical Drain. triangular configuration with spacing of 1 meter. Construction of the sand embankment is done in stages so the embankment will not collapse and increase bearing capacity (gained strength) through the consolidation process. Because of the material of the embankment is sand, so there is a potential for liquefaction, therefore the embankment need the improvement using Vibro Compaction. <br />
<br />
<br />
PLAXIS 2D will give the model for finite element method and slope stability analysis. The results of slope stability analysis by PLAXIS 2D shown the embankment conditions, earthquakes, and service life meets the requirements of SF minimum value. |
format |
Final Project |
author |
ANDRESON, REY |
author_facet |
ANDRESON, REY |
author_sort |
ANDRESON, REY |
title |
STUDY DESIGN LAMONG BAY RECLAMATION CONSTRUCTION USING GROUND IMPROVEMENT VIBRO COMPACTION AND PREFABRICATED VERTICAL DRAIN WITH FINITE ELEMENT METHOD |
title_short |
STUDY DESIGN LAMONG BAY RECLAMATION CONSTRUCTION USING GROUND IMPROVEMENT VIBRO COMPACTION AND PREFABRICATED VERTICAL DRAIN WITH FINITE ELEMENT METHOD |
title_full |
STUDY DESIGN LAMONG BAY RECLAMATION CONSTRUCTION USING GROUND IMPROVEMENT VIBRO COMPACTION AND PREFABRICATED VERTICAL DRAIN WITH FINITE ELEMENT METHOD |
title_fullStr |
STUDY DESIGN LAMONG BAY RECLAMATION CONSTRUCTION USING GROUND IMPROVEMENT VIBRO COMPACTION AND PREFABRICATED VERTICAL DRAIN WITH FINITE ELEMENT METHOD |
title_full_unstemmed |
STUDY DESIGN LAMONG BAY RECLAMATION CONSTRUCTION USING GROUND IMPROVEMENT VIBRO COMPACTION AND PREFABRICATED VERTICAL DRAIN WITH FINITE ELEMENT METHOD |
title_sort |
study design lamong bay reclamation construction using ground improvement vibro compaction and prefabricated vertical drain with finite element method |
url |
https://digilib.itb.ac.id/gdl/view/23917 |
_version_ |
1822921060553588736 |