CONSTRUCTION DELIVERY PLANNING OF LABORATORIUM UJI DOPING INSTITUT TEKNOLOGI BANDUNG
Nowadays, infrastructure development projects are emerging in this country, one of those projects is construction project of Laboratorium Uji Doping Institut Teknologi Bandung which is in maintenance phase now. Construction delivery planning is required for any construction project in order to ke...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/36559 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
Summary: | Nowadays, infrastructure development projects are emerging in this country, one of
those projects is construction project of Laboratorium Uji Doping Institut Teknologi
Bandung which is in maintenance phase now. Construction delivery planning is required
for any construction project in order to keep the construction works away from any
resistance. The purposes of this thesis are to re-planning the building’s construction
delivery planning which consists of implementation method, scheduling, and the
project’s cash flow; and also suggest a change on the implementation method which
planned by contractor.
The case study is done by observing contractor’s specification documents, bill of
quantity, and project’s S-curve. From this case study, a new idea of implementation
method can be delivered. Scheduling are planned by applying Critical Path Method and
using Microsoft Project. Scheduling is also planned with different duration from
contractor’s duration. Cash flow is planned by considering the new duration and the
change suggestion. At the final, the results are a change of material from red brick to
Celcon brick, and the project’s duration is 191 days. |
---|