THE RISK MANAGEMENT OF INTERNATIONAL EPC PROJECTS: BY THE CASE STUDY-INDONESIA S POWER PLANT PROJECT
The implementation of the strategy in China has gradually shifted many of China's general contracting engineering business from domestic to international markets. However, with the fierce competition in the international general contracting engineering market, the occurrence of financia...
Saved in:
Main Author: | |
---|---|
Format: | Theses |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/40513 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
Summary: | The implementation of the strategy in China has gradually shifted many of China's general
contracting engineering business from domestic to international markets. However, with the
fierce competition in the international general contracting engineering market, the occurrence
of financial crisis, and the uncertainty of changes in the international economic situation, the
risks of international engineering general contracting are also increasing. Many China
overseas engineering enterprises have made profits falling or even losing money in the
international engineering market. The main reason is that in addition to the external
environmental reasons and some general contractors because of internal management is not
effective, one of the most important reasons is the lack of understanding of the risk
management in the aspect of international engineering general contracting, risk and its
hazard, scientific and reasonable countermeasures and methods of risk management, which
has a great impact on the development of the international engineering general contracting
field.
ii Based on this background, the final project will be researched the risk management of
International EPC project by the case study –S power plant project and literature review. The
researcher has the work experience in the S power plant project, therefore, he knows its
situation for risk management. For case study, this research will adopted the interview
method to collect data, in accordance with the interviews result, the risks will get and display
by the research construct and risk checklist. Then, the interviewees scored the risk identified
for probability of risk occurrence and risk impact level. Depend on the probability/impact
matrix, the prioritize risks will screen out, then, give the risk response. Finally, the researcher
will identify 5 major risks that affect the implementation of international EPC projects and
give the corresponding proposed business solutions for the reference of china overseas
engineering enterprises. Due to lack historical data, thus, the qualitative risk analysis will use
for data interpretation. |
---|