PERANCANGAN DASHBOARD MONITORING DENGAN METODE EARNED VALUE MANAGEMENT DAN EARNED SCHEDULE UNTUK PROYEK PEMBANGUNAN GEDUNG PERKULIAHAN

PT XYZ is a construction company which currently handles college building construction project. Monitoring have been done using S-curve and at the time of research, project was delayed 9 weeks from baseline. The limitation of S-curve is not able to estimate cost and time of project completion. There...

Full description

Saved in:
Bibliographic Details
Main Author: FAUZANIAR, TRIANDINI
Format: Final Project
Language:Indonesia
Online Access:https://digilib.itb.ac.id/gdl/view/42386
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Institut Teknologi Bandung
Language: Indonesia
id id-itb.:42386
spelling id-itb.:423862019-09-19T10:40:57ZPERANCANGAN DASHBOARD MONITORING DENGAN METODE EARNED VALUE MANAGEMENT DAN EARNED SCHEDULE UNTUK PROYEK PEMBANGUNAN GEDUNG PERKULIAHAN FAUZANIAR, TRIANDINI Indonesia Final Project monitoring, S curve, EVM, ES, EAC, IEAC, dashboard INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/42386 PT XYZ is a construction company which currently handles college building construction project. Monitoring have been done using S-curve and at the time of research, project was delayed 9 weeks from baseline. The limitation of S-curve is not able to estimate cost and time of project completion. Therefore, this research aims to estimate project completion’s cost and time, and design the implementation of solution to PT XYZ. Earned value management (EVM) method is used to estimate project completion cost or called as estimate at completion (EAC), whereas earned schedule (ES) method is used to estimate project completion time, or known as independent estimate at completion (IEAC). Application of both methods done by Macro Excel to help company to compute and illustrate the project’s condition. Results show that the estimation of project’s completion cost is Rp14.258.931.984,81 with the duration 53,55 weeks on 29th week, cost estimation on 34th week is Rp14.303.278.417,55 with the duration 50,17 weeks, while cost estimation on 39th week is Rp14.222.775.586,60 with the duration 46,43 weeks. To make project monitoring easier, this research also develops monitoring dashboard so that estimation of project completion’s cost and time can be done at any time. It will be very beneficial for Project Manager and other stakeholders. EVM and ES computation’s result describe how long the project’s delay on cost and time. Therefore, it can detect delay and over budget that happened at the same time, so company can decide which one must be overcome first. There are some steps must be done by company to implement this method using monitoring dashboard, such as SOP arrangement, socialization, and training. text
institution Institut Teknologi Bandung
building Institut Teknologi Bandung Library
continent Asia
country Indonesia
Indonesia
content_provider Institut Teknologi Bandung
collection Digital ITB
language Indonesia
description PT XYZ is a construction company which currently handles college building construction project. Monitoring have been done using S-curve and at the time of research, project was delayed 9 weeks from baseline. The limitation of S-curve is not able to estimate cost and time of project completion. Therefore, this research aims to estimate project completion’s cost and time, and design the implementation of solution to PT XYZ. Earned value management (EVM) method is used to estimate project completion cost or called as estimate at completion (EAC), whereas earned schedule (ES) method is used to estimate project completion time, or known as independent estimate at completion (IEAC). Application of both methods done by Macro Excel to help company to compute and illustrate the project’s condition. Results show that the estimation of project’s completion cost is Rp14.258.931.984,81 with the duration 53,55 weeks on 29th week, cost estimation on 34th week is Rp14.303.278.417,55 with the duration 50,17 weeks, while cost estimation on 39th week is Rp14.222.775.586,60 with the duration 46,43 weeks. To make project monitoring easier, this research also develops monitoring dashboard so that estimation of project completion’s cost and time can be done at any time. It will be very beneficial for Project Manager and other stakeholders. EVM and ES computation’s result describe how long the project’s delay on cost and time. Therefore, it can detect delay and over budget that happened at the same time, so company can decide which one must be overcome first. There are some steps must be done by company to implement this method using monitoring dashboard, such as SOP arrangement, socialization, and training.
format Final Project
author FAUZANIAR, TRIANDINI
spellingShingle FAUZANIAR, TRIANDINI
PERANCANGAN DASHBOARD MONITORING DENGAN METODE EARNED VALUE MANAGEMENT DAN EARNED SCHEDULE UNTUK PROYEK PEMBANGUNAN GEDUNG PERKULIAHAN
author_facet FAUZANIAR, TRIANDINI
author_sort FAUZANIAR, TRIANDINI
title PERANCANGAN DASHBOARD MONITORING DENGAN METODE EARNED VALUE MANAGEMENT DAN EARNED SCHEDULE UNTUK PROYEK PEMBANGUNAN GEDUNG PERKULIAHAN
title_short PERANCANGAN DASHBOARD MONITORING DENGAN METODE EARNED VALUE MANAGEMENT DAN EARNED SCHEDULE UNTUK PROYEK PEMBANGUNAN GEDUNG PERKULIAHAN
title_full PERANCANGAN DASHBOARD MONITORING DENGAN METODE EARNED VALUE MANAGEMENT DAN EARNED SCHEDULE UNTUK PROYEK PEMBANGUNAN GEDUNG PERKULIAHAN
title_fullStr PERANCANGAN DASHBOARD MONITORING DENGAN METODE EARNED VALUE MANAGEMENT DAN EARNED SCHEDULE UNTUK PROYEK PEMBANGUNAN GEDUNG PERKULIAHAN
title_full_unstemmed PERANCANGAN DASHBOARD MONITORING DENGAN METODE EARNED VALUE MANAGEMENT DAN EARNED SCHEDULE UNTUK PROYEK PEMBANGUNAN GEDUNG PERKULIAHAN
title_sort perancangan dashboard monitoring dengan metode earned value management dan earned schedule untuk proyek pembangunan gedung perkuliahan
url https://digilib.itb.ac.id/gdl/view/42386
_version_ 1821998594044985344