INCREMENTAL DEVELOPMENT STRATEGY OF GEOTHERMAL FIELD USING WELLHEAD UNIT TECHNOLOGY: CASE STUDY ULUMBU GEOTHERMAL FIELD

Geothermal development in Indonesia is still dominated by the utilization of conventional geothermal power plants with large capacities. It generally requires a long time and often experience delays in the operation process. The purpose of this study is to provide alternative production options for...

Full description

Saved in:
Bibliographic Details
Main Author: Idianto, Onny
Format: Theses
Language:Indonesia
Online Access:https://digilib.itb.ac.id/gdl/view/48339
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Institut Teknologi Bandung
Language: Indonesia
id id-itb.:48339
spelling id-itb.:483392020-06-28T21:59:54ZINCREMENTAL DEVELOPMENT STRATEGY OF GEOTHERMAL FIELD USING WELLHEAD UNIT TECHNOLOGY: CASE STUDY ULUMBU GEOTHERMAL FIELD Idianto, Onny Indonesia Theses Incremental Development Strategy, Wellhead Unit, Ulumbu Geothermal Field, Economic Analysis, Probabilistic Approach INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/48339 Geothermal development in Indonesia is still dominated by the utilization of conventional geothermal power plants with large capacities. It generally requires a long time and often experience delays in the operation process. The purpose of this study is to provide alternative production options for field development with an incremental development strategy. This study is conducted to show the effectiveness of incremental development strategy by using a wellhead Unit compared to conventional power plants by using probibility approach with case study in the Ulumbu geothermal field, East Nusa Tenggara. In addition, this study also provides a comprehensive economic condition of the obtained revenue and project investment costs, therefore geothermal power plant development could be more feasible and minimize barriers to investment value. The methods of this study used technical analysis and economic analysis approach, from total project investment cost for each development strategy and the financial return achieved. Technical analysis is done by comparing the Specific Steam Consumption (SSC) and the amount of capacity to be generated in the power plant. The total investment value is determined using development strategies 40 MW (conventional) scenario 2x20 MW, 40 MW (incremental) scenario 8x5 MW and 40 MW (incremental) scenario 1x2,5 MW using condensing power plant. The results of the economic analysis shows that P50 from investment estimation of each 5,93 ; 5,66 and 5,68 Million USD/MW. Regarding to tariff based 80% under Average Cost of Electricity Generation (BPP) on relevant local grid, P50 Rate of Return result as 16,65%, 17,19% and 17,03%. Evaluation result are determined based on comparison of investment cost, economic parameter, tariff variation and risk assesment, incremental development scenario 8x5 MW and 16x25 MW are feasible as development alternative scenario of Ulumbu field. text
institution Institut Teknologi Bandung
building Institut Teknologi Bandung Library
continent Asia
country Indonesia
Indonesia
content_provider Institut Teknologi Bandung
collection Digital ITB
language Indonesia
description Geothermal development in Indonesia is still dominated by the utilization of conventional geothermal power plants with large capacities. It generally requires a long time and often experience delays in the operation process. The purpose of this study is to provide alternative production options for field development with an incremental development strategy. This study is conducted to show the effectiveness of incremental development strategy by using a wellhead Unit compared to conventional power plants by using probibility approach with case study in the Ulumbu geothermal field, East Nusa Tenggara. In addition, this study also provides a comprehensive economic condition of the obtained revenue and project investment costs, therefore geothermal power plant development could be more feasible and minimize barriers to investment value. The methods of this study used technical analysis and economic analysis approach, from total project investment cost for each development strategy and the financial return achieved. Technical analysis is done by comparing the Specific Steam Consumption (SSC) and the amount of capacity to be generated in the power plant. The total investment value is determined using development strategies 40 MW (conventional) scenario 2x20 MW, 40 MW (incremental) scenario 8x5 MW and 40 MW (incremental) scenario 1x2,5 MW using condensing power plant. The results of the economic analysis shows that P50 from investment estimation of each 5,93 ; 5,66 and 5,68 Million USD/MW. Regarding to tariff based 80% under Average Cost of Electricity Generation (BPP) on relevant local grid, P50 Rate of Return result as 16,65%, 17,19% and 17,03%. Evaluation result are determined based on comparison of investment cost, economic parameter, tariff variation and risk assesment, incremental development scenario 8x5 MW and 16x25 MW are feasible as development alternative scenario of Ulumbu field.
format Theses
author Idianto, Onny
spellingShingle Idianto, Onny
INCREMENTAL DEVELOPMENT STRATEGY OF GEOTHERMAL FIELD USING WELLHEAD UNIT TECHNOLOGY: CASE STUDY ULUMBU GEOTHERMAL FIELD
author_facet Idianto, Onny
author_sort Idianto, Onny
title INCREMENTAL DEVELOPMENT STRATEGY OF GEOTHERMAL FIELD USING WELLHEAD UNIT TECHNOLOGY: CASE STUDY ULUMBU GEOTHERMAL FIELD
title_short INCREMENTAL DEVELOPMENT STRATEGY OF GEOTHERMAL FIELD USING WELLHEAD UNIT TECHNOLOGY: CASE STUDY ULUMBU GEOTHERMAL FIELD
title_full INCREMENTAL DEVELOPMENT STRATEGY OF GEOTHERMAL FIELD USING WELLHEAD UNIT TECHNOLOGY: CASE STUDY ULUMBU GEOTHERMAL FIELD
title_fullStr INCREMENTAL DEVELOPMENT STRATEGY OF GEOTHERMAL FIELD USING WELLHEAD UNIT TECHNOLOGY: CASE STUDY ULUMBU GEOTHERMAL FIELD
title_full_unstemmed INCREMENTAL DEVELOPMENT STRATEGY OF GEOTHERMAL FIELD USING WELLHEAD UNIT TECHNOLOGY: CASE STUDY ULUMBU GEOTHERMAL FIELD
title_sort incremental development strategy of geothermal field using wellhead unit technology: case study ulumbu geothermal field
url https://digilib.itb.ac.id/gdl/view/48339
_version_ 1822927891684392960