IMPLEMENTATION OF LAST PLANNER SYSTEM TO IMPROVE PROJECT PRODUCTIVTY (CASE STUDY: PT. INOMATA KONSULTAMA)
PT. Inomata Konsultama is a company that does work every year from the Geospatial Information Agency (BIG) through tender mechanism. In the last 2 years, the company face the losses caused by the delay. At present, the company is collaborating on one of BIG's project called the Hydrographic...
Saved in:
Main Author: | |
---|---|
Format: | Theses |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/49373 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:49373 |
---|---|
spelling |
id-itb.:493732020-09-15T19:44:20ZIMPLEMENTATION OF LAST PLANNER SYSTEM TO IMPROVE PROJECT PRODUCTIVTY (CASE STUDY: PT. INOMATA KONSULTAMA) Surianta Sembiring, Hendra Manajemen umum Indonesia Theses Daily Huddle Meetings, Last Planner System, PPC. INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/49373 PT. Inomata Konsultama is a company that does work every year from the Geospatial Information Agency (BIG) through tender mechanism. In the last 2 years, the company face the losses caused by the delay. At present, the company is collaborating on one of BIG's project called the Hydrographic Survey Package 5, Maluku Site. Currently the company experienced decrease in productivity of the planned progress targets that have been determined during the first months to the fourth month. This is due to the eviation on plan progress with actual progress from 4.17% to 29.05% on the current total workload, this deviation caused a loss in operational costs of Rp 886,245,668.30. From the business issue, determined a root problem in the existing system in this work that occurs in the scope of work Sounding with Singlebeam and Multibeam which is the largest work activity through pareto analysis, where no collaborative design between low level workers and mid-high level workers is the main root cause of failure for companies to achieve targets in work where the Percent Plan Complete conditions are only 46%. After the root of the problem determined, the proposed scenario on alternative solutions are Business Process Redesign, Daily Huddle Meetings, Project Management Software Implementation. after the selection of the best alternative solution for the company is carried out by using the Analysis Hierarchy Process (AHP) method. In this process the stakeholders were involved to chose Daily Huddle Meetings as the best solution for PT. Inomata Konsultama with the expectation of increasing productivity on PPC to 63.57% and reducing operational costs by Rp. 266,762,148.51. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
topic |
Manajemen umum |
spellingShingle |
Manajemen umum Surianta Sembiring, Hendra IMPLEMENTATION OF LAST PLANNER SYSTEM TO IMPROVE PROJECT PRODUCTIVTY (CASE STUDY: PT. INOMATA KONSULTAMA) |
description |
PT. Inomata Konsultama is a company that does work every year from the Geospatial Information
Agency (BIG) through tender mechanism. In the last 2 years, the company face the losses caused by
the delay. At present, the company is collaborating on one of BIG's project called the Hydrographic
Survey Package 5, Maluku Site. Currently the company experienced decrease in productivity of the
planned progress targets that have been determined during the first months to the fourth month. This
is due to the eviation on plan progress with actual progress from 4.17% to 29.05% on the current
total workload, this deviation caused a loss in operational costs of Rp 886,245,668.30.
From the business issue, determined a root problem in the existing system in this work that occurs
in the scope of work Sounding with Singlebeam and Multibeam which is the largest work activity
through pareto analysis, where no collaborative design between low level workers and mid-high
level workers is the main root cause of failure for companies to achieve targets in work where the
Percent Plan Complete conditions are only 46%.
After the root of the problem determined, the proposed scenario on alternative solutions are Business
Process Redesign, Daily Huddle Meetings, Project Management Software Implementation. after the
selection of the best alternative solution for the company is carried out by using the Analysis
Hierarchy Process (AHP) method. In this process the stakeholders were involved to chose Daily
Huddle Meetings as the best solution for PT. Inomata Konsultama with the expectation of increasing
productivity on PPC to 63.57% and reducing operational costs by Rp. 266,762,148.51. |
format |
Theses |
author |
Surianta Sembiring, Hendra |
author_facet |
Surianta Sembiring, Hendra |
author_sort |
Surianta Sembiring, Hendra |
title |
IMPLEMENTATION OF LAST PLANNER SYSTEM TO IMPROVE PROJECT PRODUCTIVTY (CASE STUDY: PT. INOMATA KONSULTAMA) |
title_short |
IMPLEMENTATION OF LAST PLANNER SYSTEM TO IMPROVE PROJECT PRODUCTIVTY (CASE STUDY: PT. INOMATA KONSULTAMA) |
title_full |
IMPLEMENTATION OF LAST PLANNER SYSTEM TO IMPROVE PROJECT PRODUCTIVTY (CASE STUDY: PT. INOMATA KONSULTAMA) |
title_fullStr |
IMPLEMENTATION OF LAST PLANNER SYSTEM TO IMPROVE PROJECT PRODUCTIVTY (CASE STUDY: PT. INOMATA KONSULTAMA) |
title_full_unstemmed |
IMPLEMENTATION OF LAST PLANNER SYSTEM TO IMPROVE PROJECT PRODUCTIVTY (CASE STUDY: PT. INOMATA KONSULTAMA) |
title_sort |
implementation of last planner system to improve project productivty (case study: pt. inomata konsultama) |
url |
https://digilib.itb.ac.id/gdl/view/49373 |
_version_ |
1822928172180570112 |