LONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION

Indonesia has 124.6 billion ton coal resources according to the Ministry of Energy and Mineral Resources (2018). Coal mining system can apply an open pit mining system or an underground mining system. One of the most commonly used underground mining systems for coal is Longwall. Therefore, it is...

Full description

Saved in:
Bibliographic Details
Main Author: Maulidya, Astried
Format: Final Project
Language:Indonesia
Subjects:
Online Access:https://digilib.itb.ac.id/gdl/view/51449
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Institut Teknologi Bandung
Language: Indonesia
id id-itb.:51449
spelling id-itb.:514492020-09-28T19:54:27ZLONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION Maulidya, Astried Pertambangan dan operasi berkaitan Indonesia Final Project Longwall, design, mine development, mine production, panel support INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/51449 Indonesia has 124.6 billion ton coal resources according to the Ministry of Energy and Mineral Resources (2018). Coal mining system can apply an open pit mining system or an underground mining system. One of the most commonly used underground mining systems for coal is Longwall. Therefore, it is necessary to conduct a study for designing longwall to determine the level of production. Longwall is an underground mining system that has high production rate. After completion of mining, the mining panel is allowed to collapse just after the power roof support advances. The design of a longwall mine includes the design of the mine entry, gate entry, and mining panels. In this study, Mine designing process will use Datamine Studio Underground and Geovia Minesched for production scheduling. The longwall design is made into two designs that have differences in the number of main entries that will be used. Longwall 1 design used a three-main development consisting of main incline, auxiliary incline, and air return incline with panels at the both sides main entry. A two-main development is used in the longwall 2 design which consists of main incline and air return incline with panels at one side main entry. The gate entry used a dual heading gate road system. The mining panel has 180 m width and 3.5 m mining height. Design 1 has minable coal on the panels of 12,311,836 tonnes and 13,185,470 tonnes in longwall design 2. text
institution Institut Teknologi Bandung
building Institut Teknologi Bandung Library
continent Asia
country Indonesia
Indonesia
content_provider Institut Teknologi Bandung
collection Digital ITB
language Indonesia
topic Pertambangan dan operasi berkaitan
spellingShingle Pertambangan dan operasi berkaitan
Maulidya, Astried
LONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION
description Indonesia has 124.6 billion ton coal resources according to the Ministry of Energy and Mineral Resources (2018). Coal mining system can apply an open pit mining system or an underground mining system. One of the most commonly used underground mining systems for coal is Longwall. Therefore, it is necessary to conduct a study for designing longwall to determine the level of production. Longwall is an underground mining system that has high production rate. After completion of mining, the mining panel is allowed to collapse just after the power roof support advances. The design of a longwall mine includes the design of the mine entry, gate entry, and mining panels. In this study, Mine designing process will use Datamine Studio Underground and Geovia Minesched for production scheduling. The longwall design is made into two designs that have differences in the number of main entries that will be used. Longwall 1 design used a three-main development consisting of main incline, auxiliary incline, and air return incline with panels at the both sides main entry. A two-main development is used in the longwall 2 design which consists of main incline and air return incline with panels at one side main entry. The gate entry used a dual heading gate road system. The mining panel has 180 m width and 3.5 m mining height. Design 1 has minable coal on the panels of 12,311,836 tonnes and 13,185,470 tonnes in longwall design 2.
format Final Project
author Maulidya, Astried
author_facet Maulidya, Astried
author_sort Maulidya, Astried
title LONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION
title_short LONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION
title_full LONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION
title_fullStr LONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION
title_full_unstemmed LONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION
title_sort longwall mining design with two-entry system and three-entry system for main entry and coal production estimation
url https://digilib.itb.ac.id/gdl/view/51449
_version_ 1822000953838010368