LONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION
Indonesia has 124.6 billion ton coal resources according to the Ministry of Energy and Mineral Resources (2018). Coal mining system can apply an open pit mining system or an underground mining system. One of the most commonly used underground mining systems for coal is Longwall. Therefore, it is...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/51449 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:51449 |
---|---|
spelling |
id-itb.:514492020-09-28T19:54:27ZLONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION Maulidya, Astried Pertambangan dan operasi berkaitan Indonesia Final Project Longwall, design, mine development, mine production, panel support INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/51449 Indonesia has 124.6 billion ton coal resources according to the Ministry of Energy and Mineral Resources (2018). Coal mining system can apply an open pit mining system or an underground mining system. One of the most commonly used underground mining systems for coal is Longwall. Therefore, it is necessary to conduct a study for designing longwall to determine the level of production. Longwall is an underground mining system that has high production rate. After completion of mining, the mining panel is allowed to collapse just after the power roof support advances. The design of a longwall mine includes the design of the mine entry, gate entry, and mining panels. In this study, Mine designing process will use Datamine Studio Underground and Geovia Minesched for production scheduling. The longwall design is made into two designs that have differences in the number of main entries that will be used. Longwall 1 design used a three-main development consisting of main incline, auxiliary incline, and air return incline with panels at the both sides main entry. A two-main development is used in the longwall 2 design which consists of main incline and air return incline with panels at one side main entry. The gate entry used a dual heading gate road system. The mining panel has 180 m width and 3.5 m mining height. Design 1 has minable coal on the panels of 12,311,836 tonnes and 13,185,470 tonnes in longwall design 2. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
topic |
Pertambangan dan operasi berkaitan |
spellingShingle |
Pertambangan dan operasi berkaitan Maulidya, Astried LONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION |
description |
Indonesia has 124.6 billion ton coal resources according to the Ministry of Energy and
Mineral Resources (2018). Coal mining system can apply an open pit mining system or an
underground mining system. One of the most commonly used underground mining systems
for coal is Longwall.
Therefore, it is necessary to conduct a study for designing longwall to determine the level of
production. Longwall is an underground mining system that has high production rate. After
completion of mining, the mining panel is allowed to collapse just after the power roof
support advances. The design of a longwall mine includes the design of the mine entry, gate
entry, and mining panels. In this study, Mine designing process will use Datamine Studio
Underground and Geovia Minesched for production scheduling.
The longwall design is made into two designs that have differences in the number of main
entries that will be used. Longwall 1 design used a three-main development consisting of
main incline, auxiliary incline, and air return incline with panels at the both sides main
entry. A two-main development is used in the longwall 2 design which consists of main
incline and air return incline with panels at one side main entry. The gate entry used a dual
heading gate road system. The mining panel has 180 m width and 3.5 m mining height.
Design 1 has minable coal on the panels of 12,311,836 tonnes and 13,185,470 tonnes in
longwall design 2. |
format |
Final Project |
author |
Maulidya, Astried |
author_facet |
Maulidya, Astried |
author_sort |
Maulidya, Astried |
title |
LONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION |
title_short |
LONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION |
title_full |
LONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION |
title_fullStr |
LONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION |
title_full_unstemmed |
LONGWALL MINING DESIGN WITH TWO-ENTRY SYSTEM AND THREE-ENTRY SYSTEM FOR MAIN ENTRY AND COAL PRODUCTION ESTIMATION |
title_sort |
longwall mining design with two-entry system and three-entry system for main entry and coal production estimation |
url |
https://digilib.itb.ac.id/gdl/view/51449 |
_version_ |
1822000953838010368 |