ANALYSIS OF THE IMPACT OF BLASTING TUNNEL # 4 ON THE JAKARTA-BANDUNG FAST TRAIN PROJECT ON RESIDENCE
PT. SINOHYDRO together with PT. Kereta Cepat Indonesia Cina (KCIC) is currently working on the Jakarta-Bandung fast train tunnel construction project. One of the tunnels currently being worked on is tunnel # 4 in Sukatani District, Purwakarta Regency. Tunnel # 4 is planned to use mechanical excav...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/51665 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:51665 |
---|---|
spelling |
id-itb.:516652020-09-29T21:33:39ZANALYSIS OF THE IMPACT OF BLASTING TUNNEL # 4 ON THE JAKARTA-BANDUNG FAST TRAIN PROJECT ON RESIDENCE Pratama, Rengga Pertambangan dan operasi berkaitan Indonesia Final Project Scaled Distance (SD) , Peak Vector Sum (PVS), Peak Particle Acceleration (PPA), Peak Particle Displacement (PPD). INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/51665 PT. SINOHYDRO together with PT. Kereta Cepat Indonesia Cina (KCIC) is currently working on the Jakarta-Bandung fast train tunnel construction project. One of the tunnels currently being worked on is tunnel # 4 in Sukatani District, Purwakarta Regency. Tunnel # 4 is planned to use mechanical excavation for soft materials in the form of silty clay and silty sand and blasting methods for hard materials in the form of andesite rock. This research was conducted with the aim of predicting the amount of PVS, PPA, and PPD as a result of the blasting in the vicinity of tunnel # 4 KCIC. Data was collected directly in the field using the Instantel "Minimate Plus" tool. Data processing was processed using the Blastware application and Microsoft Excel. The impact of blasting in tunnel # 4 does not exceed the NAB (Threshold Value) of vibration for Class 1 SNI 7571: 2010, namely PVS = 3 mm / all frequency = 5-20 Hz. The impact of the blasting did not increase the value of the fracture in the community houses around tunnel # 4. From the results of data processing, the predicted values of Peak Vector Sum (PVS), Peak Particle Acceleration (PPA), Peak Particle Displacement (PPD) were obtained. With the equation PVS = 747.6 SD -1.48, PPA = 79.89 SD -1.64, PPD = 5.94 SD -1.6 text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
topic |
Pertambangan dan operasi berkaitan |
spellingShingle |
Pertambangan dan operasi berkaitan Pratama, Rengga ANALYSIS OF THE IMPACT OF BLASTING TUNNEL # 4 ON THE JAKARTA-BANDUNG FAST TRAIN PROJECT ON RESIDENCE |
description |
PT. SINOHYDRO together with PT. Kereta Cepat Indonesia Cina (KCIC) is
currently working on the Jakarta-Bandung fast train tunnel construction project.
One of the tunnels currently being worked on is tunnel # 4 in Sukatani District,
Purwakarta Regency. Tunnel # 4 is planned to use mechanical excavation for soft
materials in the form of silty clay and silty sand and blasting methods for hard
materials in the form of andesite rock. This research was conducted with the aim of
predicting the amount of PVS, PPA, and PPD as a result of the blasting in the
vicinity of tunnel # 4 KCIC. Data was collected directly in the field using the
Instantel "Minimate Plus" tool. Data processing was processed using the Blastware
application and Microsoft Excel. The impact of blasting in tunnel # 4 does not exceed
the NAB (Threshold Value) of vibration for Class 1 SNI 7571: 2010, namely PVS = 3
mm / all frequency = 5-20 Hz. The impact of the blasting did not increase the value
of the fracture in the community houses around tunnel # 4. From the results of data
processing, the predicted values of Peak Vector Sum (PVS), Peak Particle
Acceleration (PPA), Peak Particle Displacement (PPD) were obtained. With the
equation PVS = 747.6 SD -1.48, PPA = 79.89 SD -1.64, PPD = 5.94 SD -1.6 |
format |
Final Project |
author |
Pratama, Rengga |
author_facet |
Pratama, Rengga |
author_sort |
Pratama, Rengga |
title |
ANALYSIS OF THE IMPACT OF BLASTING TUNNEL # 4 ON THE JAKARTA-BANDUNG FAST TRAIN PROJECT ON RESIDENCE |
title_short |
ANALYSIS OF THE IMPACT OF BLASTING TUNNEL # 4 ON THE JAKARTA-BANDUNG FAST TRAIN PROJECT ON RESIDENCE |
title_full |
ANALYSIS OF THE IMPACT OF BLASTING TUNNEL # 4 ON THE JAKARTA-BANDUNG FAST TRAIN PROJECT ON RESIDENCE |
title_fullStr |
ANALYSIS OF THE IMPACT OF BLASTING TUNNEL # 4 ON THE JAKARTA-BANDUNG FAST TRAIN PROJECT ON RESIDENCE |
title_full_unstemmed |
ANALYSIS OF THE IMPACT OF BLASTING TUNNEL # 4 ON THE JAKARTA-BANDUNG FAST TRAIN PROJECT ON RESIDENCE |
title_sort |
analysis of the impact of blasting tunnel # 4 on the jakarta-bandung fast train project on residence |
url |
https://digilib.itb.ac.id/gdl/view/51665 |
_version_ |
1822001021400907776 |