ANALYSIS OF INITIAL SUPPORT DESIGN OF SAMARINDA TUNNEL STA 0+425 USING H-BEAM WITH 3D MODELING
The Samarinda tunnel has a horseshoe geometry, egg-shaped with a 10.5 m vertical length and 12.8 horizontal length which will be excavated using the top and bench method. STA 0+425 (BH-04) is the deepest tunnel construction with a depth of 62 m and is in sandstone lithology. Therefore it is neces...