ANALYSIS OF INITIAL SUPPORT DESIGN OF SAMARINDA TUNNEL STA 0+425 USING H-BEAM WITH 3D MODELING
The Samarinda tunnel has a horseshoe geometry, egg-shaped with a 10.5 m vertical length and 12.8 horizontal length which will be excavated using the top and bench method. STA 0+425 (BH-04) is the deepest tunnel construction with a depth of 62 m and is in sandstone lithology. Therefore it is neces...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/76814 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
Be the first to leave a comment!