CAPACITY AND LEVEL OF PERFORMANCE OF MOTORWAY ON-RAMP B AT CAWANG INTERCHANGE, JAKARTA
Abstract: <br /> <br /> <br /> Merging process of on-ramp entering the main road may affect the free flow speed, bunching characteristic, and overtaking maneuver of vehicle, and finally will affect the level of performance of the on-ramp and the main road. <br /> <br /&g...
Saved in:
Main Author: | |
---|---|
Format: | Theses |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/9223 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:9223 |
---|---|
spelling |
id-itb.:92232017-09-27T15:21:03ZCAPACITY AND LEVEL OF PERFORMANCE OF MOTORWAY ON-RAMP B AT CAWANG INTERCHANGE, JAKARTA Winarno (NIM 269 93 026), Sapto Indonesia Theses INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/9223 Abstract: <br /> <br /> <br /> Merging process of on-ramp entering the main road may affect the free flow speed, bunching characteristic, and overtaking maneuver of vehicle, and finally will affect the level of performance of the on-ramp and the main road. <br /> <br /> <br /> The objectives of the study are: to evaluate the performance and to calculate the capacity of the ramp junction, and to determine its level of service using US-HCM94. This research also study how vehicle speed is affected by the merging process. <br /> <br /> <br /> The research was conducted on Cawang Interchange (RampB) of Cawang-Tomang Toll Road section between sta.1+600 and sta.1+800. The interchange has two-lane one-way on-ramp, and the main road before merging is a four-lane two-way divided road. The main road after merging is a six-lane two-way divided road. The width of paved shoulder for all section is 200 m and the side friction is low. <br /> <br /> <br /> Data collection was carried out on Monday from 6.30 a.m. to 5.30 p.m. using two camcorder videos which were installed on a multi story building in the study area. Further data processing was conducted using ITravel computer program which produced Speed-Flow-Density relationship. <br /> <br /> <br /> The result of study indicated that at on-peak hour between 08.15 a.m. to 08.45 a.m., congestion occurred in the road link. This is indicated by the low vehicle speed of less then 15 km/hr. It is found in this study that the capacity of the on-ramp is about 2236 pcu/h/lane. And the capacity of the main road is about 2760 pcu/h/lane. This shows that the capacity of road with similar condition calculated by IHCM 97. By referring to US-HCM it is found that the Level of Service of the ramp junction is F. <br /> text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
description |
Abstract: <br />
<br />
<br />
Merging process of on-ramp entering the main road may affect the free flow speed, bunching characteristic, and overtaking maneuver of vehicle, and finally will affect the level of performance of the on-ramp and the main road. <br />
<br />
<br />
The objectives of the study are: to evaluate the performance and to calculate the capacity of the ramp junction, and to determine its level of service using US-HCM94. This research also study how vehicle speed is affected by the merging process. <br />
<br />
<br />
The research was conducted on Cawang Interchange (RampB) of Cawang-Tomang Toll Road section between sta.1+600 and sta.1+800. The interchange has two-lane one-way on-ramp, and the main road before merging is a four-lane two-way divided road. The main road after merging is a six-lane two-way divided road. The width of paved shoulder for all section is 200 m and the side friction is low. <br />
<br />
<br />
Data collection was carried out on Monday from 6.30 a.m. to 5.30 p.m. using two camcorder videos which were installed on a multi story building in the study area. Further data processing was conducted using ITravel computer program which produced Speed-Flow-Density relationship. <br />
<br />
<br />
The result of study indicated that at on-peak hour between 08.15 a.m. to 08.45 a.m., congestion occurred in the road link. This is indicated by the low vehicle speed of less then 15 km/hr. It is found in this study that the capacity of the on-ramp is about 2236 pcu/h/lane. And the capacity of the main road is about 2760 pcu/h/lane. This shows that the capacity of road with similar condition calculated by IHCM 97. By referring to US-HCM it is found that the Level of Service of the ramp junction is F. <br />
|
format |
Theses |
author |
Winarno (NIM 269 93 026), Sapto |
spellingShingle |
Winarno (NIM 269 93 026), Sapto CAPACITY AND LEVEL OF PERFORMANCE OF MOTORWAY ON-RAMP B AT CAWANG INTERCHANGE, JAKARTA |
author_facet |
Winarno (NIM 269 93 026), Sapto |
author_sort |
Winarno (NIM 269 93 026), Sapto |
title |
CAPACITY AND LEVEL OF PERFORMANCE OF MOTORWAY ON-RAMP B AT CAWANG INTERCHANGE, JAKARTA |
title_short |
CAPACITY AND LEVEL OF PERFORMANCE OF MOTORWAY ON-RAMP B AT CAWANG INTERCHANGE, JAKARTA |
title_full |
CAPACITY AND LEVEL OF PERFORMANCE OF MOTORWAY ON-RAMP B AT CAWANG INTERCHANGE, JAKARTA |
title_fullStr |
CAPACITY AND LEVEL OF PERFORMANCE OF MOTORWAY ON-RAMP B AT CAWANG INTERCHANGE, JAKARTA |
title_full_unstemmed |
CAPACITY AND LEVEL OF PERFORMANCE OF MOTORWAY ON-RAMP B AT CAWANG INTERCHANGE, JAKARTA |
title_sort |
capacity and level of performance of motorway on-ramp b at cawang interchange, jakarta |
url |
https://digilib.itb.ac.id/gdl/view/9223 |
_version_ |
1820664630577463296 |