Productivity aspects of driven pile operations in Singapore
This study presents findings on pre-cast reinforced concrete driven pile productivity levels. Measurements were made for two case studies on pre-cast reinforced concrete piles utilising a performance indicator for bored piling recently developed by Lee & Mahmood. A comparison has been made betwe...
Saved in:
Main Author: | |
---|---|
Other Authors: | |
Format: | Theses and Dissertations |
Published: |
2008
|
Subjects: | |
Online Access: | http://hdl.handle.net/10356/6659 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Nanyang Technological University |
id |
sg-ntu-dr.10356-6659 |
---|---|
record_format |
dspace |
spelling |
sg-ntu-dr.10356-66592020-09-26T21:20:18Z Productivity aspects of driven pile operations in Singapore Hor, Puey Sheng. Lim, Ewe Chye Centre for Advanced Construction Studies DRNTU::Engineering::Civil engineering::Geotechnical This study presents findings on pre-cast reinforced concrete driven pile productivity levels. Measurements were made for two case studies on pre-cast reinforced concrete piles utilising a performance indicator for bored piling recently developed by Lee & Mahmood. A comparison has been made between the productivity levels of these two driven piles case studies, namely a condominium and a commercial building. Factors influencing productivity performance of driven piles have been highlighted. A comparison has been made on the productivity levels of the above two piling systems, namely bored piling (after Lee & Mahmood) and driven piles used by the author. Productivity levels for the driven piles case studies are found to be consistently higher than the productivity levels for the projects using the bored pile system. Conclusions made indicated that a driven pre-cast reinforced pile system offers an economically viable alternative. Advantages and limitations of the productivity model for wider application have also been reviewed and presented. This study also proposes methods to raise and solve some of the issues affecting productivity problems in Singapore. Master of Science (International Construction Management) 2008-09-17T11:50:19Z 2008-09-17T11:50:19Z 2000 2000 Thesis http://hdl.handle.net/10356/6659 Nanyang Technological University application/pdf |
institution |
Nanyang Technological University |
building |
NTU Library |
country |
Singapore |
collection |
DR-NTU |
topic |
DRNTU::Engineering::Civil engineering::Geotechnical |
spellingShingle |
DRNTU::Engineering::Civil engineering::Geotechnical Hor, Puey Sheng. Productivity aspects of driven pile operations in Singapore |
description |
This study presents findings on pre-cast reinforced concrete driven pile productivity levels. Measurements were made for two case studies on pre-cast reinforced concrete piles utilising a performance indicator for bored piling recently developed by Lee & Mahmood. A comparison has been made between the productivity levels of these two driven piles case studies, namely a condominium and a commercial building. Factors influencing productivity performance of driven piles have been highlighted. A comparison has been made on the productivity levels of the above two piling systems, namely bored piling (after Lee & Mahmood) and driven piles used by the author. Productivity levels for the driven piles case studies are found to be consistently higher than the productivity levels for the projects using the bored pile system. Conclusions made indicated that a driven pre-cast reinforced pile system offers an economically viable alternative. Advantages and limitations of the productivity model for wider application have also been reviewed and presented. This study also proposes methods to raise and solve some of the issues affecting productivity problems in Singapore. |
author2 |
Lim, Ewe Chye |
author_facet |
Lim, Ewe Chye Hor, Puey Sheng. |
format |
Theses and Dissertations |
author |
Hor, Puey Sheng. |
author_sort |
Hor, Puey Sheng. |
title |
Productivity aspects of driven pile operations in Singapore |
title_short |
Productivity aspects of driven pile operations in Singapore |
title_full |
Productivity aspects of driven pile operations in Singapore |
title_fullStr |
Productivity aspects of driven pile operations in Singapore |
title_full_unstemmed |
Productivity aspects of driven pile operations in Singapore |
title_sort |
productivity aspects of driven pile operations in singapore |
publishDate |
2008 |
url |
http://hdl.handle.net/10356/6659 |
_version_ |
1681058709019557888 |