CRITICAL PATH ANALYSIS FOR MULTI-BLOCK COMBINED CYCLE POWER PLANT CONSTRUCTION ON LIMITED WORK AREA USING CPM

Power plant construction becomes such a crucial thing in the era when energy has grown into such an inevitable demand on modern human civilization. Limited natural resources become a major trigger for implementation of high-efficiency power plant. Advances in science and technology have succeeded on...

Full description

Saved in:
Bibliographic Details
Main Author: MART CAHYA (NIM : 13205120); Pembimbing : Dr. Ir. Yusra Sabri, FAZAR
Format: Final Project
Language:Indonesia
Online Access:https://digilib.itb.ac.id/gdl/view/15651
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Institut Teknologi Bandung
Language: Indonesia
id id-itb.:15651
spelling id-itb.:156512017-09-27T10:18:35ZCRITICAL PATH ANALYSIS FOR MULTI-BLOCK COMBINED CYCLE POWER PLANT CONSTRUCTION ON LIMITED WORK AREA USING CPM MART CAHYA (NIM : 13205120); Pembimbing : Dr. Ir. Yusra Sabri, FAZAR Indonesia Final Project INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/15651 Power plant construction becomes such a crucial thing in the era when energy has grown into such an inevitable demand on modern human civilization. Limited natural resources become a major trigger for implementation of high-efficiency power plant. Advances in science and technology have succeeded on increasing efficiency of natural gas powered power plant by utilizing the exhaust gas energy from gas turbine exhaustion to generate steam, so a single power plant unit could have two termodynamic cycles. This kind of power plant is called Combined Cycle Power Plant. The complexity of the Combined Cycle Power Plant system, and problems like land use limitation, have made the construction of Combined Cycle Power Plant Blocks very hard. The comprehension on electical power project management becomes a must-have matter so the construction developes in an effective and efficient way despite of any technical and natural limitation. The project management method that will be used is Critical Path Analysis Method. This method is a method that utilize network model as a graphical representation of the interrelation between construction activities on the base of project work duration. The construction of Combined Cycle Power Plant on limited work area has particular problems on the construction method. Specific insight on the problems derives some distinctive construction methods. Work scenarios which are made from different construction methods sure have a very different consequences on fulfilling fundamental aspects of a project, such as time and money efficiency, process effectivitiy, keeping a low risk and high quality. <br /> <br /> <br /> Analysis from this method will be done by referring to the possible construction scenarios. The breakdown details will be compared in three key parameters: time, cost, and risk, by consideration of a well kept quality and effectivity, except the probabilty of the very parameter intercorelation shows a different implication. text
institution Institut Teknologi Bandung
building Institut Teknologi Bandung Library
continent Asia
country Indonesia
Indonesia
content_provider Institut Teknologi Bandung
collection Digital ITB
language Indonesia
description Power plant construction becomes such a crucial thing in the era when energy has grown into such an inevitable demand on modern human civilization. Limited natural resources become a major trigger for implementation of high-efficiency power plant. Advances in science and technology have succeeded on increasing efficiency of natural gas powered power plant by utilizing the exhaust gas energy from gas turbine exhaustion to generate steam, so a single power plant unit could have two termodynamic cycles. This kind of power plant is called Combined Cycle Power Plant. The complexity of the Combined Cycle Power Plant system, and problems like land use limitation, have made the construction of Combined Cycle Power Plant Blocks very hard. The comprehension on electical power project management becomes a must-have matter so the construction developes in an effective and efficient way despite of any technical and natural limitation. The project management method that will be used is Critical Path Analysis Method. This method is a method that utilize network model as a graphical representation of the interrelation between construction activities on the base of project work duration. The construction of Combined Cycle Power Plant on limited work area has particular problems on the construction method. Specific insight on the problems derives some distinctive construction methods. Work scenarios which are made from different construction methods sure have a very different consequences on fulfilling fundamental aspects of a project, such as time and money efficiency, process effectivitiy, keeping a low risk and high quality. <br /> <br /> <br /> Analysis from this method will be done by referring to the possible construction scenarios. The breakdown details will be compared in three key parameters: time, cost, and risk, by consideration of a well kept quality and effectivity, except the probabilty of the very parameter intercorelation shows a different implication.
format Final Project
author MART CAHYA (NIM : 13205120); Pembimbing : Dr. Ir. Yusra Sabri, FAZAR
spellingShingle MART CAHYA (NIM : 13205120); Pembimbing : Dr. Ir. Yusra Sabri, FAZAR
CRITICAL PATH ANALYSIS FOR MULTI-BLOCK COMBINED CYCLE POWER PLANT CONSTRUCTION ON LIMITED WORK AREA USING CPM
author_facet MART CAHYA (NIM : 13205120); Pembimbing : Dr. Ir. Yusra Sabri, FAZAR
author_sort MART CAHYA (NIM : 13205120); Pembimbing : Dr. Ir. Yusra Sabri, FAZAR
title CRITICAL PATH ANALYSIS FOR MULTI-BLOCK COMBINED CYCLE POWER PLANT CONSTRUCTION ON LIMITED WORK AREA USING CPM
title_short CRITICAL PATH ANALYSIS FOR MULTI-BLOCK COMBINED CYCLE POWER PLANT CONSTRUCTION ON LIMITED WORK AREA USING CPM
title_full CRITICAL PATH ANALYSIS FOR MULTI-BLOCK COMBINED CYCLE POWER PLANT CONSTRUCTION ON LIMITED WORK AREA USING CPM
title_fullStr CRITICAL PATH ANALYSIS FOR MULTI-BLOCK COMBINED CYCLE POWER PLANT CONSTRUCTION ON LIMITED WORK AREA USING CPM
title_full_unstemmed CRITICAL PATH ANALYSIS FOR MULTI-BLOCK COMBINED CYCLE POWER PLANT CONSTRUCTION ON LIMITED WORK AREA USING CPM
title_sort critical path analysis for multi-block combined cycle power plant construction on limited work area using cpm
url https://digilib.itb.ac.id/gdl/view/15651
_version_ 1820737514804084736