IMPLEMENTATION STUDY OF RELIABILITY CENTERED MAINTENANCE ON BELT CONVEYOR 13 AND 14 SURALAYA POWER PLANT UNIT 1-4

PLTU Suralaya Unit 1-4 with a capacity of 4x400 MW is a power plant with major contribution in the Java Madura Bali (JAMALI) electricity system. The reliability operation of the plant is influenced by several factors, one of which is coal distribution system. <br /> <br /> <br />...

Full description

Saved in:
Bibliographic Details
Main Author: ABIDIN (NIM : 23108311); Pembimbing:Prof. Dr. Ir. Indra Nurhadi, ZAINAL
Format: Theses
Language:Indonesia
Online Access:https://digilib.itb.ac.id/gdl/view/17712
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Institut Teknologi Bandung
Language: Indonesia
id id-itb.:17712
spelling id-itb.:177122017-09-27T14:53:48ZIMPLEMENTATION STUDY OF RELIABILITY CENTERED MAINTENANCE ON BELT CONVEYOR 13 AND 14 SURALAYA POWER PLANT UNIT 1-4 ABIDIN (NIM : 23108311); Pembimbing:Prof. Dr. Ir. Indra Nurhadi, ZAINAL Indonesia Theses INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/17712 PLTU Suralaya Unit 1-4 with a capacity of 4x400 MW is a power plant with major contribution in the Java Madura Bali (JAMALI) electricity system. The reliability operation of the plant is influenced by several factors, one of which is coal distribution system. <br /> <br /> <br /> Equipment belt conveyor BC 13 and the BC 14 is the "heart" of the coal delivery system to Unit 1-4. Failure on both of these belt conveyor will have an impact on the decrease in electricity production in the power plant. <br /> <br /> <br /> To maintain the reliability of equipment BC 13 and BC 14 is necessary appropriate maintenance strategy. Reliability-based maintenance strategy or reliability centered maintenance (RCM) on both the equipment is expected to be able to maintain their reliability. <br /> <br /> <br /> Determination of the appropriate type of maintenance: run-to-failure, preventive, predictive or proactive maintenance is intended to get the effective and efficient maintenance in terms of time and maintenance costs. text
institution Institut Teknologi Bandung
building Institut Teknologi Bandung Library
continent Asia
country Indonesia
Indonesia
content_provider Institut Teknologi Bandung
collection Digital ITB
language Indonesia
description PLTU Suralaya Unit 1-4 with a capacity of 4x400 MW is a power plant with major contribution in the Java Madura Bali (JAMALI) electricity system. The reliability operation of the plant is influenced by several factors, one of which is coal distribution system. <br /> <br /> <br /> Equipment belt conveyor BC 13 and the BC 14 is the "heart" of the coal delivery system to Unit 1-4. Failure on both of these belt conveyor will have an impact on the decrease in electricity production in the power plant. <br /> <br /> <br /> To maintain the reliability of equipment BC 13 and BC 14 is necessary appropriate maintenance strategy. Reliability-based maintenance strategy or reliability centered maintenance (RCM) on both the equipment is expected to be able to maintain their reliability. <br /> <br /> <br /> Determination of the appropriate type of maintenance: run-to-failure, preventive, predictive or proactive maintenance is intended to get the effective and efficient maintenance in terms of time and maintenance costs.
format Theses
author ABIDIN (NIM : 23108311); Pembimbing:Prof. Dr. Ir. Indra Nurhadi, ZAINAL
spellingShingle ABIDIN (NIM : 23108311); Pembimbing:Prof. Dr. Ir. Indra Nurhadi, ZAINAL
IMPLEMENTATION STUDY OF RELIABILITY CENTERED MAINTENANCE ON BELT CONVEYOR 13 AND 14 SURALAYA POWER PLANT UNIT 1-4
author_facet ABIDIN (NIM : 23108311); Pembimbing:Prof. Dr. Ir. Indra Nurhadi, ZAINAL
author_sort ABIDIN (NIM : 23108311); Pembimbing:Prof. Dr. Ir. Indra Nurhadi, ZAINAL
title IMPLEMENTATION STUDY OF RELIABILITY CENTERED MAINTENANCE ON BELT CONVEYOR 13 AND 14 SURALAYA POWER PLANT UNIT 1-4
title_short IMPLEMENTATION STUDY OF RELIABILITY CENTERED MAINTENANCE ON BELT CONVEYOR 13 AND 14 SURALAYA POWER PLANT UNIT 1-4
title_full IMPLEMENTATION STUDY OF RELIABILITY CENTERED MAINTENANCE ON BELT CONVEYOR 13 AND 14 SURALAYA POWER PLANT UNIT 1-4
title_fullStr IMPLEMENTATION STUDY OF RELIABILITY CENTERED MAINTENANCE ON BELT CONVEYOR 13 AND 14 SURALAYA POWER PLANT UNIT 1-4
title_full_unstemmed IMPLEMENTATION STUDY OF RELIABILITY CENTERED MAINTENANCE ON BELT CONVEYOR 13 AND 14 SURALAYA POWER PLANT UNIT 1-4
title_sort implementation study of reliability centered maintenance on belt conveyor 13 and 14 suralaya power plant unit 1-4