DECISION ANALYSIS IN DETERMINING MANPOWER RESOURCES TO IMPROVE PERFORMANCE OF THE LOWER WANAGON PROJECT PT FREEPORT INDONESIA

Each mining company has accountability to ensure all affected areas due to mining <br /> <br /> operation are in good condition prior to close and leave the mine. As part of mine closure <br /> <br /> plan of Grasberg open pit mine, Lower Wanagon project is very critical for...

Full description

Saved in:
Bibliographic Details
Main Author: HOTLAN NAPITU 29115272, AGUS
Format: Theses
Language:Indonesia
Online Access:https://digilib.itb.ac.id/gdl/view/20819
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Institut Teknologi Bandung
Language: Indonesia
id id-itb.:20819
spelling id-itb.:208192017-10-02T14:43:07ZDECISION ANALYSIS IN DETERMINING MANPOWER RESOURCES TO IMPROVE PERFORMANCE OF THE LOWER WANAGON PROJECT PT FREEPORT INDONESIA HOTLAN NAPITU 29115272, AGUS Indonesia Theses INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/20819 Each mining company has accountability to ensure all affected areas due to mining <br /> <br /> operation are in good condition prior to close and leave the mine. As part of mine closure <br /> <br /> plan of Grasberg open pit mine, Lower Wanagon project is very critical for PT Freeport <br /> <br /> Indonesia. Lower Wanagon project objectives is to comply with reclamation commitment <br /> <br /> and to guarantee the geotechnical stability of Lower Wanagon Overburden Stockpiles, the <br /> <br /> largest waste rock stockpiles in Grasberg open pit mine, PT Freeport Indonesia. Lower <br /> <br /> Wanagon project was initially planned to complete in 2024. <br /> <br /> The completion of Lower Wanagon project as per design and schedule is a key concern for <br /> <br /> company as it will directly impact to environmental and social issues. Failure to achieve <br /> <br /> target will potentially lead PT Freeport Indonesia to a catastrophic risk. Therefore, many <br /> <br /> efforts has been done by company including dedicated a business unit, equipment and <br /> <br /> material for this project execution. Nevertheless, the project performance is very poor. The <br /> <br /> project is currently behind the target about three years and cost increasing significantly <br /> <br /> from USD 700 million to USD 840 million due to this delay. This delay will also escalate <br /> <br /> the landslide potential, one of catastrophic risk faced by company. <br /> <br /> This final project is intended to analyze and study the issues regarding poor project <br /> <br /> performance in Lower Wanagon project, find out the root cause as well as provide best <br /> <br /> recommendation in order to speed up the progress and improve project performance. Cause <br /> <br /> and effect (fishbone) diagram is utilized as a tool to find out the root causes. Analytic <br /> <br /> Hierarchy Process (AHP) method is used to solve the root causes by determining and <br /> <br /> evaluating the best business unit to finish Lower Wanagon project. <br /> <br /> The AHP calculation resulted in business unit of Petrosea as the best solution to finish <br /> <br /> Lower Wanagon project with consolidated weight of 0.4044. With this solution, it is <br /> <br /> confidently projected that the project completion will be faster about three years from <br /> <br /> actual condition or project can be finished as per original target and saving money (avoid <br /> <br /> potential additional cost) about USD 87.6 million. The solution also will lower the potential <br /> <br /> risk of landslide from high to low and preserve company reputation regarding best mining <br /> <br /> practice and compliance to government regulation. text
institution Institut Teknologi Bandung
building Institut Teknologi Bandung Library
continent Asia
country Indonesia
Indonesia
content_provider Institut Teknologi Bandung
collection Digital ITB
language Indonesia
description Each mining company has accountability to ensure all affected areas due to mining <br /> <br /> operation are in good condition prior to close and leave the mine. As part of mine closure <br /> <br /> plan of Grasberg open pit mine, Lower Wanagon project is very critical for PT Freeport <br /> <br /> Indonesia. Lower Wanagon project objectives is to comply with reclamation commitment <br /> <br /> and to guarantee the geotechnical stability of Lower Wanagon Overburden Stockpiles, the <br /> <br /> largest waste rock stockpiles in Grasberg open pit mine, PT Freeport Indonesia. Lower <br /> <br /> Wanagon project was initially planned to complete in 2024. <br /> <br /> The completion of Lower Wanagon project as per design and schedule is a key concern for <br /> <br /> company as it will directly impact to environmental and social issues. Failure to achieve <br /> <br /> target will potentially lead PT Freeport Indonesia to a catastrophic risk. Therefore, many <br /> <br /> efforts has been done by company including dedicated a business unit, equipment and <br /> <br /> material for this project execution. Nevertheless, the project performance is very poor. The <br /> <br /> project is currently behind the target about three years and cost increasing significantly <br /> <br /> from USD 700 million to USD 840 million due to this delay. This delay will also escalate <br /> <br /> the landslide potential, one of catastrophic risk faced by company. <br /> <br /> This final project is intended to analyze and study the issues regarding poor project <br /> <br /> performance in Lower Wanagon project, find out the root cause as well as provide best <br /> <br /> recommendation in order to speed up the progress and improve project performance. Cause <br /> <br /> and effect (fishbone) diagram is utilized as a tool to find out the root causes. Analytic <br /> <br /> Hierarchy Process (AHP) method is used to solve the root causes by determining and <br /> <br /> evaluating the best business unit to finish Lower Wanagon project. <br /> <br /> The AHP calculation resulted in business unit of Petrosea as the best solution to finish <br /> <br /> Lower Wanagon project with consolidated weight of 0.4044. With this solution, it is <br /> <br /> confidently projected that the project completion will be faster about three years from <br /> <br /> actual condition or project can be finished as per original target and saving money (avoid <br /> <br /> potential additional cost) about USD 87.6 million. The solution also will lower the potential <br /> <br /> risk of landslide from high to low and preserve company reputation regarding best mining <br /> <br /> practice and compliance to government regulation.
format Theses
author HOTLAN NAPITU 29115272, AGUS
spellingShingle HOTLAN NAPITU 29115272, AGUS
DECISION ANALYSIS IN DETERMINING MANPOWER RESOURCES TO IMPROVE PERFORMANCE OF THE LOWER WANAGON PROJECT PT FREEPORT INDONESIA
author_facet HOTLAN NAPITU 29115272, AGUS
author_sort HOTLAN NAPITU 29115272, AGUS
title DECISION ANALYSIS IN DETERMINING MANPOWER RESOURCES TO IMPROVE PERFORMANCE OF THE LOWER WANAGON PROJECT PT FREEPORT INDONESIA
title_short DECISION ANALYSIS IN DETERMINING MANPOWER RESOURCES TO IMPROVE PERFORMANCE OF THE LOWER WANAGON PROJECT PT FREEPORT INDONESIA
title_full DECISION ANALYSIS IN DETERMINING MANPOWER RESOURCES TO IMPROVE PERFORMANCE OF THE LOWER WANAGON PROJECT PT FREEPORT INDONESIA
title_fullStr DECISION ANALYSIS IN DETERMINING MANPOWER RESOURCES TO IMPROVE PERFORMANCE OF THE LOWER WANAGON PROJECT PT FREEPORT INDONESIA
title_full_unstemmed DECISION ANALYSIS IN DETERMINING MANPOWER RESOURCES TO IMPROVE PERFORMANCE OF THE LOWER WANAGON PROJECT PT FREEPORT INDONESIA
title_sort decision analysis in determining manpower resources to improve performance of the lower wanagon project pt freeport indonesia
url https://digilib.itb.ac.id/gdl/view/20819
_version_ 1821120274664259584