OPTIMAL COST ANALYSIS FOR PROJECT SCHEDULE ACCELERATION (CASE STUDY: MOTHER AND CHILD HOSPITAL CONSTRUCTION PROJECT OF DR. HASAN SADIKIN BANDUNG)
Indonesia, with a population of over 275 million, faces significant challenges in improving infrastructure due to its archipelagic geography. The Indonesian government has been striving to accelerate infrastructure development through the National Long-Term Development Plan (RPJPN) 2025-2045 to s...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/82574 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:82574 |
---|---|
spelling |
id-itb.:825742024-07-09T09:31:00ZOPTIMAL COST ANALYSIS FOR PROJECT SCHEDULE ACCELERATION (CASE STUDY: MOTHER AND CHILD HOSPITAL CONSTRUCTION PROJECT OF DR. HASAN SADIKIN BANDUNG) Rizki Khairi, Fajar Teknik sipil Indonesia Final Project Project Schedule Acceleration, Optimum Cost, Floor-to-Floor Scheme INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/82574 Indonesia, with a population of over 275 million, faces significant challenges in improving infrastructure due to its archipelagic geography. The Indonesian government has been striving to accelerate infrastructure development through the National Long-Term Development Plan (RPJPN) 2025-2045 to support the Vision of Golden Indonesia 2045, including strengthening health infrastructure. This study focuses on accelerating the project schedule for the construction of the Mother and Child Service Center at Hasan Sadikin Hospital Bandung, particularly on structural works such as beams, columns, slabs, and shear walls. The aim of the research is to identify applicable acceleration alternatives and analyze their impact on the construction project schedule. The methodology used is a quantitative approach using empirical data to develop a project scheduling optimization model. The research results show that indirect costs are not significant to the optimal cost of project acceleration, with a percentage between 4-6%. The optimal scenario was found in the floor-to-floor 6-day alternative with an additional cost per day of Rp302,206,723.20 or 0.397% of the total cost under normal conditions. This study provides significant contributions to construction project management through a deductive approach and quantitative analysis, which can help practitioners and researchers improve the efficiency and effectiveness of project management. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
topic |
Teknik sipil |
spellingShingle |
Teknik sipil Rizki Khairi, Fajar OPTIMAL COST ANALYSIS FOR PROJECT SCHEDULE ACCELERATION (CASE STUDY: MOTHER AND CHILD HOSPITAL CONSTRUCTION PROJECT OF DR. HASAN SADIKIN BANDUNG) |
description |
Indonesia, with a population of over 275 million, faces significant challenges in
improving infrastructure due to its archipelagic geography. The Indonesian
government has been striving to accelerate infrastructure development through the
National Long-Term Development Plan (RPJPN) 2025-2045 to support the Vision
of Golden Indonesia 2045, including strengthening health infrastructure. This study
focuses on accelerating the project schedule for the construction of the Mother and
Child Service Center at Hasan Sadikin Hospital Bandung, particularly on structural
works such as beams, columns, slabs, and shear walls. The aim of the research is to
identify applicable acceleration alternatives and analyze their impact on the
construction project schedule. The methodology used is a quantitative approach
using empirical data to develop a project scheduling optimization model. The
research results show that indirect costs are not significant to the optimal cost of
project acceleration, with a percentage between 4-6%. The optimal scenario was
found in the floor-to-floor 6-day alternative with an additional cost per day of
Rp302,206,723.20 or 0.397% of the total cost under normal conditions. This study
provides significant contributions to construction project management through a
deductive approach and quantitative analysis, which can help practitioners and
researchers improve the efficiency and effectiveness of project management. |
format |
Final Project |
author |
Rizki Khairi, Fajar |
author_facet |
Rizki Khairi, Fajar |
author_sort |
Rizki Khairi, Fajar |
title |
OPTIMAL COST ANALYSIS FOR PROJECT SCHEDULE ACCELERATION (CASE STUDY: MOTHER AND CHILD HOSPITAL CONSTRUCTION PROJECT OF DR. HASAN SADIKIN BANDUNG) |
title_short |
OPTIMAL COST ANALYSIS FOR PROJECT SCHEDULE ACCELERATION (CASE STUDY: MOTHER AND CHILD HOSPITAL CONSTRUCTION PROJECT OF DR. HASAN SADIKIN BANDUNG) |
title_full |
OPTIMAL COST ANALYSIS FOR PROJECT SCHEDULE ACCELERATION (CASE STUDY: MOTHER AND CHILD HOSPITAL CONSTRUCTION PROJECT OF DR. HASAN SADIKIN BANDUNG) |
title_fullStr |
OPTIMAL COST ANALYSIS FOR PROJECT SCHEDULE ACCELERATION (CASE STUDY: MOTHER AND CHILD HOSPITAL CONSTRUCTION PROJECT OF DR. HASAN SADIKIN BANDUNG) |
title_full_unstemmed |
OPTIMAL COST ANALYSIS FOR PROJECT SCHEDULE ACCELERATION (CASE STUDY: MOTHER AND CHILD HOSPITAL CONSTRUCTION PROJECT OF DR. HASAN SADIKIN BANDUNG) |