PERFORMANCE ANALYSIS OF UPPER PART TUNNELING CYCLE OF THE XYZ TUNNEL
The XYZ Tunnel Project is a double track railroad tunnel through 473 meters of <br /> <br /> hills with the inlet side at KM 359 + 155 and the outlet side at KM 359 + 628. <br /> <br /> Tunneling using New Austrian Tunneling Method (NATM) is focused to complete <br /> &...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/25488 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:25488 |
---|---|
spelling |
id-itb.:254882018-07-02T09:51:20ZPERFORMANCE ANALYSIS OF UPPER PART TUNNELING CYCLE OF THE XYZ TUNNEL INDRA SUBROTO (NIM : 12114006), ANDHIKA Indonesia Final Project INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/25488 The XYZ Tunnel Project is a double track railroad tunnel through 473 meters of <br /> <br /> hills with the inlet side at KM 359 + 155 and the outlet side at KM 359 + 628. <br /> <br /> Tunneling using New Austrian Tunneling Method (NATM) is focused to complete <br /> <br /> the upper part of the tunnel so that the inlet and outlet sides are connected within <br /> <br /> the planned time. <br /> <br /> One of the project management is to optimize a cycle of upper tunnel well. <br /> <br /> Optimization is done on the timing of each stage of tunneling, obstacle analysis that <br /> <br /> makes the work is not running optimally, and the availability of tools. Data to <br /> <br /> perform the optimization is done by recording daily activities consisting of the <br /> <br /> timing of each stage of tunneling, working hours per equipment, and other records <br /> <br /> outside the activities of direct field observers. <br /> <br /> The observation results show that the acceleration system can increase the <br /> <br /> performance of upper part tunneling of XYZ Tunnel. The upper part tunneling <br /> <br /> cycle of the XYZ Tunnel is not in accordance with the New Austrian Tunneling <br /> <br /> Method (NATM) because the activity is not done in the proper sequence. Physical <br /> <br /> Availabilty equipment is above 90%. Work in series causes Effective Utilization <br /> <br /> (EU) value to be below 50% because equipment is only used in accordance with its <br /> <br /> working time only. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
description |
The XYZ Tunnel Project is a double track railroad tunnel through 473 meters of <br />
<br />
hills with the inlet side at KM 359 + 155 and the outlet side at KM 359 + 628. <br />
<br />
Tunneling using New Austrian Tunneling Method (NATM) is focused to complete <br />
<br />
the upper part of the tunnel so that the inlet and outlet sides are connected within <br />
<br />
the planned time. <br />
<br />
One of the project management is to optimize a cycle of upper tunnel well. <br />
<br />
Optimization is done on the timing of each stage of tunneling, obstacle analysis that <br />
<br />
makes the work is not running optimally, and the availability of tools. Data to <br />
<br />
perform the optimization is done by recording daily activities consisting of the <br />
<br />
timing of each stage of tunneling, working hours per equipment, and other records <br />
<br />
outside the activities of direct field observers. <br />
<br />
The observation results show that the acceleration system can increase the <br />
<br />
performance of upper part tunneling of XYZ Tunnel. The upper part tunneling <br />
<br />
cycle of the XYZ Tunnel is not in accordance with the New Austrian Tunneling <br />
<br />
Method (NATM) because the activity is not done in the proper sequence. Physical <br />
<br />
Availabilty equipment is above 90%. Work in series causes Effective Utilization <br />
<br />
(EU) value to be below 50% because equipment is only used in accordance with its <br />
<br />
working time only. |
format |
Final Project |
author |
INDRA SUBROTO (NIM : 12114006), ANDHIKA |
spellingShingle |
INDRA SUBROTO (NIM : 12114006), ANDHIKA PERFORMANCE ANALYSIS OF UPPER PART TUNNELING CYCLE OF THE XYZ TUNNEL |
author_facet |
INDRA SUBROTO (NIM : 12114006), ANDHIKA |
author_sort |
INDRA SUBROTO (NIM : 12114006), ANDHIKA |
title |
PERFORMANCE ANALYSIS OF UPPER PART TUNNELING CYCLE OF THE XYZ TUNNEL |
title_short |
PERFORMANCE ANALYSIS OF UPPER PART TUNNELING CYCLE OF THE XYZ TUNNEL |
title_full |
PERFORMANCE ANALYSIS OF UPPER PART TUNNELING CYCLE OF THE XYZ TUNNEL |
title_fullStr |
PERFORMANCE ANALYSIS OF UPPER PART TUNNELING CYCLE OF THE XYZ TUNNEL |
title_full_unstemmed |
PERFORMANCE ANALYSIS OF UPPER PART TUNNELING CYCLE OF THE XYZ TUNNEL |
title_sort |
performance analysis of upper part tunneling cycle of the xyz tunnel |
url |
https://digilib.itb.ac.id/gdl/view/25488 |
_version_ |
1822921574204833792 |