PERFORMANCE ANALYSIS OF UPPER PART TUNNELING CYCLE OF THE XYZ TUNNEL
The XYZ Tunnel Project is a double track railroad tunnel through 473 meters of <br /> <br /> hills with the inlet side at KM 359 + 155 and the outlet side at KM 359 + 628. <br /> <br /> Tunneling using New Austrian Tunneling Method (NATM) is focused to complete <br /> &...
Saved in:
Main Author: | INDRA SUBROTO (NIM : 12114006), ANDHIKA |
---|---|
Format: | Final Project |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/25488 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
Similar Items
-
VENTILATION ANALYSIS OF XYZ TUNNEL CONSTRUCTION AT CENTRAL JAVA PROVINCE
by: AZIZ (NIM : 12114047), ABDUL -
TUNNEL MONITORING WITH TOTAL STATION ON NOTOG RAILWAY TUNNEL
by: Prima Sudibyo (NIM : 22115009), Surya -
ANALYSIS OF AIR DISTRIBUTION AND TEMPERATURE CONDITIONS IN THE DEVELOPMENT TUNNEL OF PT XYZ USING COMPUTATIONAL FLUID DYNAMICS.
by: Limowa, Agung -
ROADHEADER PERFORMANCE ANALYSIS FOR NANJUNG WATER TUNNEL EXCAVATION
by: Wahyu Hidayat, Dhany -
ANALYSIS THE EFFECT OF JOINT SPACING AND JOINT ORIENTATION OF TWIN HEADER̉̉S PRODUCTIVITY ON EXCAVATION OF TUNNEL XYZ
by: Tridinata - Nim: 12114087 , Prastyo